Invitation for Construction Bid: Boiler Economizer Replacement Project
Change Order
Published Tuesday July 8, 2008
Contractor: Mid-Illinois Mechanical
Change Order amount: $61,856

This change order is the result of additional work identified during the construction phase of the project.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Friday April 4, 2008
Awarded to:
Contractor: Mid-Illinois Mechanical, Bloomington, IL
Amount: $190,000
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 0
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Monday, February 25, 2008
Project Description
Illinois State University requests sealed bids for the Boiler Economizer Replacement project. This project involves the replacement of boiler economizers at the Illinois State University Heating Plant.
Sealed bids will be accepted at the address below until 2:00 PM, Thursday, March 20, 2008:
Purchasing Office
117 Hovey Hall
Normal, IL 61790-1220
There is a mandatory pre-bid meeting on March 6, 2008 at 10:30 AM at the Illinois State University Heating Plant on University street south of College Avenue, Illinois State University, Normal, Illinois, 61790. If you are planning to submit a prime bid for this project, you must attend this meeting and your comnpany name must appear on the official attendance log. This log will be used in the bid opening process, and if your company name does not appear on the log, your bid will not be opened.

For additional information, contact:
Robyn Schuline
Campus Box 1220
Illinois State University
Normal, IL 61790-1220
Phone: (309) 438-5529
FAX: (309) 438-5555
E-Mail: rsschul@ilstu.edu
All responses must include:
  • Submit 2 copies of the response as defined in the specifications.
  • Sealed envelopes containing the bids have the bid number and project title on the envelope.
  • Bid security (see complete bid for details).
  • A letter from a surety company in substantially the form set forth in the Instructions to Bidders assuring the issuance of the performance and payment bonds.