To obtain documents, log on:
:
Not registered? Register me now
 

Public Higher Education Bulletin

 
Illinois State University
Bid #RB042006
Invitation for Construction Bid: Wright Residence Hall Renovation Project
Change Order
Published Tuesday March 18, 2008
Change Order amount: $44,291

This change order applies to Commercial Mechanical (Heating Contractor) and is for additional work identified during the construction phase of the project.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Tuesday August 7, 2007
Change Order amount: $47,342

This change order applies to McCoy construction (General contractor) and is for additional work identified during construction.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday June 1, 2007
Change Order amount: $39,991

This change order applies to McWilliams Mechanical (plumbing contractor) and is for additional work identified during construction to allow for compliance with Plumbing Code requirements.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Thursday May 24, 2007
Change Order amount: $76,331

This change order applies to McCoy construction (General contractor) and is for additional work identified during construction.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Monday May 15, 2006
Awarded to:
Contractor: McCoy Construction, Pontiac, Illinois
Amount:  $3,473,000
Division of Work: General Contractor (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Foster-Jacob, Peoria, Illinois
Amount:  $778,000
Division of Work: Electrical (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: A&R Mechanical, Urbana, Illinois
Amount:  $186,670
Division of Work: Ventilation (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Commerical Mechanical, Dunlap, Illinois
Amount:  $658,800
Division of Work: Heating (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: McWilliams Mechanical, Champaign, Illinois
Amount:  $649,800
Division of Work: Plumbing (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: McDaniels, Fire Systems, Champaign, Illinois
Amount:  $272,978
Division of Work: Sprinkler System (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 16
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Friday, March 24, 2006
Sealed bids will be accepted at the address below until 2:00 PM, Thursday, April 20, 2006:
Purchasing Office
117 Hovey Hall
Normal, IL 61790-1220
Bidding documents may be obtained from BBA Engineering, P.C., Attn: Wright Hall, 1509 North Clinton Blvd, Bloomington, Illinois 61701., Phone: 309-829-9458, Fax: 309-829-4142, E-mail: jkummer@bbaeng.com.
There is a mandatory pre-bid meeting on April 6, 2006 at 2:00 PM CST at the Linkins Dining Center Private Dining Room, West Campus, Illinois State University, Normal, Illinois, 61790. If you are planning to submit a prime bid for this project, you must attend this meeting and your company name must appear on the official attendance log. This log will be used in the bid opening process, and if your company name does not appear on the log, your bid will not be opened.

For additional information, contact:
Robyn Schuline
Campus Box 1220
Illinois State University
Normal, IL 61790-1220
Phone: (309) 438-5529
FAX: (309) 438-5555
E-Mail: rsschul@ilstu.edu
All responses must include:
  • Submit 1 copies of the response as defined in the specifications.
  • Sealed envelopes containing the bids have the bid number and project title on the envelope.
  • Bid security (see complete bid for details).
  • A letter from a surety company in substantially the form set forth in the Instructions to Bidders assuring the issuance of the performance and payment bonds.

Bulletin Navigation

 