Invitation for Construction Bid: Hancock Stadium Turf Replacement

Change Order
Published Thursday October 4, 2007
 
Change order amount: $65,948.91

Additional work was required due to unforeseen items and conditions identified during the construction phase of the project.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info
Published Wednesday January 3, 2007
 
Awarded to:
Contractor:  Cooling Landscape, Cherry Valley, IL
Amount:  $1,241,855
Terms:   One-time transaction
Number of Unsuccessful, Responsive Bidders: 1
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Wednesday November 8, 2006
Project Description
This project involves the removal of existing synthetic turf, its asphalt base and sufficient earth sub-base to accomodate installation of new aggregate, drain pipes and synthetic turf. Construction of new concrete retaining walls with masonry face brick will also be included. Relocation and addition of electrical receptacles as well as additional communications conduit, conductors and terminal boxes are included as well.
General contractors
Sealed bids will be accepted at the address below until 2:00 PM, Thursday December 14, 2006:
Purchasing Office
117 Hovey Hall
Normal, IL 61790-1220
There is a mandatory pre-bid meeting on December 5, 2006 at 10:00 AM local time at the Kaufman Football Building Main Conference Room(N.E. corner of Hancock Stadium), Illinois State University, Normal, Illinois, 61790. If you are planning to submit a prime bid for this project, you must attend this meeting and your company name must appear on the official attendance log. This log will be used in the bid opening process, and if your company name does not appear on the log, your bid will not be opened.
Drawings and specifications may be obtained at the office of Hurst-Rosche Engineers, Inc., PH# 217-787-1199, 2657 West Lawrence Avenue, Springfield, Illinois after 11/13/06 by paying a refundable deposit of $100 for each set. The deposit is refundable if plans are returned to the Architect/Engineer within 10 days of the bid date without markings placed thereon or sheets that have been torn, stained or otherwise physically damaged.
For additional information, contact:
Robyn Schuline
Campus Box 1220
Illinois State University
Normal, IL 61790-1220
Phone: (309) 438-5529
FAX: (309) 438-5555
E-Mail: rsschul@ilstu.edu
Purchasing Website
All responses must include:
  • Submit 2 copies of the response as defined in the specifications.
  • Sealed envelopes containing the bids have the bid number and project title on the envelope.