Bid #E13375-0125M

Invitation for Construction Bid: Metal Siding and Roof Replacement

Award Info
Published Tuesday June 29, 2004
 
Awarded to:
Contractor:  Schimpf Construction, Inc., Carbondale, IL
Amount:  $234,850
Terms:   One-time transaction
Number of Unsuccessful, Responsive Bidders: 4
Comments:
Base Bid for Building #0213
Option #1 (1)
Option #1 (2)
Option #3 (2)
Option #3 (3)
Option #4 (2)
Option #4 (3)

Also Base Bid for Building #0214
Option #1 (1)
Option #1 (2)

The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Monday June 7, 2004
Sealed bids will be accepted at the address below until 2:00 PM, Tuesday June 22, 2004:
Purchasing Office
108 Miles Hall
Southern Illinois University Carbondale
Carbondale, IL 62901-6813

The Board of Trustees of Southern Illinois University Carbondale hereby requests sealed bids for construction work on the metal siding and roof replacement project.

This bid is to furnish all equipment, labor and material to remove existing metal siding and install new metal siding for the University Press Building and the Museum Storage Building on the Carbondale campus. Both buildings shall also have a new metal roof installed over the existing metal roof with new insulation to be provided under the new roof. All work to be done as called for and noted in drawings provided as part of the bid package.

The Contractor must have all work, siding, roof and insulation installation completed by July 31, 2004.

An award will be made to the lowest responsible and responsive Bidder based on base bid and any accepted alternate bids, if any. The University may choose to award any or all alternates based on the availability of funds, if found to be in the best interest of the University.

Bids will be received up to the hour of 2:00 PM local time, on Tuesday, June 22, 2004. Immediately after closing time for receiving bids, they will be opened publicly and read.

All bids must include:

  • Bid security (see complete bid for details)
  • All bidders must submit a PC-2 form as required by the Illinois Department of Human Rights.

A pre-bid meeting to discuss this project will be held on June 14, 2004 at 10 a.m. CDST in the Conference Roof at Physical Plant Services on the Carbondale campus.

(Submitted by Cathy Hagler, State Purchasing Officer.)