To obtain documents, log on:
:
Not registered? Register me now
 

Public Higher Education Bulletin

 
Southern Illinois University Edwardsville
Emergency Award #8593

Announcement of an Emergency Award/Quick Purchase

Final Amount
Published Tuesday August 21, 2007
 
Final amount: $68,361

A change order was processed in the amount of $1,041 to replace existing cardboard deflectors at transfer grilles with sheet metal deflectors.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info
Published Tuesday June 19, 2007
 
Awarded to:
Vendor:  Jen Mechanical, Alton, IL
Amount:  An estimated $67,320
Terms:   One-time transaction
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Tuesday June 19, 2007
The University awarded a contract for ventilation work in the gross anatomy lab.
This emergency/quick purchase was required due to a situation in which public health or safety was threatened
The University solicited informal quotes to reconstruct the ventilation and air handling system in the Gross Anatomy Lab at the School of Dental Medicine. Air samples were taken by an industrial hygiene firm indicating a possibility that our students and staff are being exposed to a level of chemical fumes which is higher than the recommended exposure limit.
Because class is scheduled to begin in August, it is critical that we get this project completed before that date. According to the Environmental Health and Safety officer at SIUE, this is a significant life safety issue.
For additional information, contact:
Shelly Albert
Purchasing Campus Box 1012
Southern Illinois University Edwardsville
Edwardsville, IL 62026-1012
Phone: (618) 650-3265
FAX: (618) 650-3251
E-Mail: malbert@siue.edu

Bulletin Navigation

 
No documents are available.