To obtain documents, log on:
:
Not registered? Register me now
 

Public Higher Education Bulletin

 
University of Illinois at Urbana-Champaign
QBS #00N05

Request for Professional Services Qualifications (QBS): Computer Science Building

Amendment
Published Monday June 21, 2004
 
Amendment amount: $35,831

This change order is for the roofing work to add S5 copper panels.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday March 5, 2004
 
Amendment amount: $59,741

The change is for changes in the diffuser locations due to conflicts.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday August 20, 2003
 
Amendment amount: $45,010

The change is for providing limestone relief at the stair tower.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday August 20, 2003
 
Amendment amount: $51,544

The change is for adding fin tube covers to the project.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday August 20, 2003
 
Amendment amount: $55,416

The change is for relocating conduit on the first floor to avoid conflict above the ceiling.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday August 20, 2003
 
Amendment amount: $60,977

The change is for the revised power and data base on Departmental furnishings.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday August 20, 2003
 
Amendment amount: $37,590

This change order is for electrical work to revised power for the furniture location.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday August 20, 2003
 
Amendment amount: $74,286

The change order is for electrical work on smart panels and kiosks.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $54,354

The change is for additional roller shades.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $213,566

The change is for the monumental stair cost over the allowance.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $135,253

The change is for a revised schedule for delay in start of construction.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $97,827

The change is for gutter modification.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $52,670

The change is for the revised Stoughton St. design base on campus direction.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $62,070

The change is for the revised proximity readers.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Monday July 21, 2003
 
Amendment amount: $46,010

The change is for interior signage difference.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $36,285

The change is for the additional telecomm duct banc for infrastructure.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $174,497

The change is for the revised design of Stoughton Street.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $54,626

The change is for the scope work for the steam tunnel.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $158,730

The change is for an increase in reimbursables - printing, travel, and models.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Friday July 18, 2003
 
Amendment amount: $143,019

The change is for the additional electronic door hardware.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Thursday July 17, 2003
 
Amendment amount: $51,505

The project is for enhancing switch electric entrance equipment.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Thursday July 17, 2003
 
Amendment amount: $51,505

The change is for the enhanced switch electric entrance equipment.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Thursday July 17, 2003
 
Amendment amount: $44,390

The change is for revised project schedule for windows and entrance work.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Thursday July 17, 2003
 
Amendment amount: $44,390

The change is for a revised project schedule for windows and entrance work.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday July 16, 2003
 
Amendment amount: $96,307

The change is for door hardware modifications.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday July 16, 2003
 
Amendment amount: $44,390

The change is for revised project schedule for windows and entrance work.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday July 16, 2003
 
Amendment amount: $46,470

The change is for a revised concrete schedule.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday July 16, 2003
 
Amendment amount: $30,864

The change is for the revised schedule for excavation work.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday July 16, 2003
 
Amendment amount: $73,440

The change is for spreading soil at the receiving site.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday July 9, 2003
 
Amendment amount: $52,500

The change is for the extended bid date.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Tuesday July 8, 2003
 
Amendment amount: $135,500

This change is for CCSO Hub/IT/Storm Water (utilities work)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info
Published Monday July 24, 2000
 
Awarded to:
Consultant:  LZT Architects, Inc., Peoria, IL
Amount:  $746,000
Terms:   One-time transaction
Number of Unsuccessful, Responsive Respondents: 4
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Thursday January 20, 2000
Qualifications and supporting materials will be accepted at the address below until 4:00 PM, Friday February 11, 2000:
University of Illinois at Urbana-Champaign
207 Henry Administration Building
506 South Wright Street
Urbana, IL 61801-3684

Project Description
The Department of Computer Science at the University of Illinois at Urbana-Champaign is recognized throughout the world as a leader in education and research. Poised on the verge of a tremendous growth spurt and to accommodate this expansion the College of Engineering has identified a new private gift which, matched with state funds, will construct a new facility for the Department of Computer Science. The $74 million project will construct a 270,000 gsf. facility of classroom, office, and computer laboratory space for the Department of Computer Science. The project will be located directly east of Newmark Laboratory in the area bounded by Stoughton (south), White (north), Mathews (west), and Goodwin (east).

Proposals
Firms should submit four copies of the following: a letter of interest, a copy of its CDB prequalification letter, and a 255 form (use CDB SF 255 dated 7/1/98) by 4:00 p.m., Friday, February 11, 2000 addressed to:

University of Illinois
Office for Project Planning & Facility Management
Illini Union Bookstore
807 S. Wright St., Suite 320
Champaign, IL 61820
Attention: Roland R. Kehe, AIA
Email address: rkehe@uiuc.edu

Architect/Engineer selection will be consistent with the Illinois Procurement Code.

Only those firms which meet the following qualifications will be considered for selection:

  • Licensed to practice as an architect in the State of Illinois.
  • Prequalified with the State of Illinois Capital Development Board
  • Business presence in Illinois
  • Utilization of AutoCAD compatible system
(Submitted by Katharine Kral, State Purchasing Officer.)

Selection will be consistent with the Architectural, Engineering, and Land Surveying Qualifications Based Selection Act (30 ILCS 535/1).

Bulletin Navigation

 
No documents are available.