The Board of Trustees of U of Illinois Facilities Planning and Programs hereby requests sealed bids for construction work on the Electrical Distribution Phase V - Electrical Substation and Infrastructure Component at Urbana Campus project.
Project Description
This project consists of the installation of electrical ductlines in the area around Abbott Power Plant to tie the new mainstation to the existing electrical feeder system; the construction of a new electrical switchgear building at the Veterinary Medicine Boiler plant location with installation of electrical ductlines in the area leading to it; and the installation of electrical equipment at the southeast substation.
Bid Proposals
Submit all proposals to the Board of Trustees at:
The Board of Trustees of the University of Illinois
c/o the Office for Project Planning & Facility Management
Illini Union Bookstore
807 S. Wright St., Suite 320
Champaign, IL 61820.
ATTN: Jim Spese, j-spese@uiuc.edu
Bids will be received up to the hour of 2:00 PM local time, on Tuesday, August 14, 2001. Immediately after closing time for receiving bids, they will be opened publicly and read.
Pre-Bid Conference
A pre-bid conference will be held in Room 128 of the Physical Plant Services Building, 1501 South Oak Street, Champaign, IL 61820 at 9:00 a.m. prevailing time on Tuesday, July 31, 2001. Representatives of the owner and the architect/engineer will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.
(Submitted by Katharine Kral, State Purchasing Officer.)