To obtain documents, log on:
:
Not registered? Register me now
 

Public Higher Education Bulletin

 
University of Illinois at Urbana-Champaign
Bid #03C10

Invitation for Construction Bid: Abbott Power Plant Expansion

Change Order
Published Thursday February 24, 2005
 
Change order amount: $736,400

This change is for additional architectural/engineering services.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday July 18, 2003
 
Change order amount: $33,768

The change is for LO pump relief valves, Steam TG, steam driven LO pump, and exhaust relief valves.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday July 18, 2003
 
Change order amount: $57,900

The change is for the A/E services modification number seven.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday July 18, 2003
 
Change order amount: $89,000

This change is for Amendment #4.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday July 18, 2003
 
Change order amount: $88,900

The change is for the A/E services correct input.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info
Published Thursday May 22, 2003
 
Awarded to:
Contractor:  Iowa Pipeline Association, Inc., Council Bluffs, IA
Amount:  $870,000
Terms:   One-time transaction
Number of Unsuccessful, Responsive Bidders: 3
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Monday April 21, 2003
Sealed bids will be accepted at the address below until 3:00 PM, Tuesday May 6, 2003:
University of Illinois at Urbana-Champaign
207 Henry Administration Building
506 South Wright Street
Urbana, IL 61801-3684

The Board of Trustees of U of Illinois Facilities Planning and Programs hereby requests sealed bids for construction work on the Abbott Power Plant Expansion and Rehabilitation Gas Line Extension at the Urbana -Champaign Campus project.

Project Description
The project consists of the installation of approximately 10,000 feet of 10" gas main along with 3 regulator stations, the installation of 2700' of 6" PE main, and 8800' of two pair-2" flexible non metallic conduit. The project will include the repair of all streets and sidewalks.

Bid Dates
Submit all proposals to the Board of Trustees at:

The Board of Trustees of the University of Illinois
c/o Planning, Construction & Maintenance
1501 S. Oak Street
Champaign, IL 61820
attn: John Kaczmarek, Project Manager (jfkaczma@uiuc.edu)

Bids will be received up to the hour of 3:00 PM local time, on Tuesday, May 6, 2003. Immediately after closing time for receiving bids, they will be opened publicly and read.

Pre-Bid Conference
A pre-bid conference will be held at in at the Physical Plant Service Building, Room 128, 1501 South Oak Street, Champaign, Illinois, at 11:00 a.m. prevailing time on April 25, 2003. Representatives of the owner and the architect/engineer will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.

(Submitted by Katharine Kral, State Purchasing Officer.)

Bulletin Navigation

 
No documents are available.