Awarded to:Contractor: Rausch Construction Company, Inc, Broadview, IL
Amount: $16,031,200
Division of Work: 1 - General (unsuccessful, responsive bidders: )
Terms: One-time transaction
Contractor: McWilliams Mechanical Svc. Inc., Champaign, IL
Amount: $576,600
Division of Work: 2 - Plumbing (unsuccessful, responsive bidders: )
Terms: One-time transaction
Contractor: Nogle and Black Mechanical Inc., Urbana, IL
Amount: $96,900
Division of Work: 3 - Heating (unsuccessful, responsive bidders: )
Terms: One-time transaction
Contractor: A&R Mechanical Contactors, Inc., Urbana, IL
Amount: $220,000
Division of Work: 4 - Vent & Air Distr (unsuccessful, responsive bidders: )
Terms: One-time transaction
Contractor: Glesco Electric, Inc., Urbana, IL
Amount: $1,212,200
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: )
Terms: One-time transaction
Number of unsuccessful, responsive bidders: Comments:
The low bid amount was accepted for each division.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Sealed bids will be accepted at the address below until 3:00 PM, Tuesday, June 24, 2003:
The Board of Trustees of
U of Illinois Facilities Planning and Programs
hereby requests sealed bids for construction work on the
South Farms Relocation, Phase One Implementation at the Urbana Campus project.
Project Description
The project consists of performing construction of a new beef/sheep unit, renovation and new construction of summer pasture (working facility), and off site utility extensions. The work includes, but is not limited to the following:
- Work indicated by contract documents, dated May 28, 2003, prepared by A. Epstein and Sons International Inc., 600 West Fulton Street, Chicago, Illinois 60661.
- New beef/sheep unit consisting of 1 office building, 18 agricultural buildings/barns, 10 above ground glass lined steel tanks, 3 grain silos, site utilities (natural gas, electric, telecommunications, water, sewer, storm sewer), detention ponds, parking lot and internal gravel roads.
- Renovation and new construction of summer pasture (working facility) consisting of modification to existing animal working facility, construction of 6 new shade structures, and a construction of a gravel road.
- Off site utilities consisting of water mains, natural gas, electrical and telecommunications (conduit, fiber optic, and copper twisted pair).
- Miscellaneous associated work, except for work performed by owner or under separate contracts.
Refer to Division 1, Section 01110 - Summary of Work of the specification for a complete, detailed breakdown of the base bids and alternates for this project.
Bid Dates
Bids will be received up to the hour of 10:00 a.m. prevailing time, on June 24, 2003, for Divisions II through V work. Bids will be received up to the hour of 3:00 p.m. prevailing time, on June 24, 2003 for Division I work. Submit all proposals to the Board of Trustees at:
The Board of Trustees of the University of Illinois
c/o Planning, Construction & Maintenance
1501 South Oak Street
Champaign, IL 61820
ATTN: Kevin Duff, kevind@uiuc.edu.
Bids will be received up to the hour of
3:00 PM
local time, on
Tuesday, June 24, 2003.
Immediately after closing time for receiving bids, they will be opened publicly and read.
Pre-Bid Conference
A pre-bid conference will be held Room 128 Physical Plant, 1501 S. Oak Street, Champaign, Illinois, 61820 at 1:30 p.m. prevailing time on June 10, 2003. Representatives of the owner and the architect/engineer will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.
(Submitted by designee Thomas Delanty, State Purchasing Officer.)