Bid #BA04C22

Invitation for Construction Bid: Huff Hall Electrical Upgrade

Award Info
Published Tuesday January 18, 2005
 
Awarded to:
Contractor:  Multiple bidders:
  • Commercial Builders, Inc. - Urbana, IL ($182,934 for Division I - General Work)
  • Reliable Plumbing and Heating Co. - Savoy, IL ($3000 for Division III - Heating, Piping, Refrigeration, & Temperature Control Work)
  • Reliable Plumbing and Heating Co. - Savoy, IL ($28,035 for Division IV - Ventilation & Air Distribution Work)
  • Bodine Electric - Champaign, IL ($112,499 for Division V - Electrical Work)

Amount:  A total of $326,468
Terms:   One-time transaction
Number of Unsuccessful, Responsive Bidders: 8
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Friday July 16, 2004
Sealed bids will be accepted at the address below until 2:00 PM, Tuesday August 3, 2004:
University of Illinois at Urbana-Champaign
207 Henry Administration Building
506 South Wright Street
Urbana, IL 61801-3684

The Board of Trustees of U of Illinois Facilities Planning and Programs hereby requests sealed bids for construction work on the the Huff Hall Electrical Upgrade at the Urbana campus project.

Project Description
This project consists of selective demolition of masonry partitions, mechanical/ventilation system and electrical components, new CMU partitions, hollow metal doors, frames & hardware, and painting. A new, owner approved, 15KV pad mounted switchgear will be installed by the electrical contractor outside of the building. A new, owner approved, 1000/1333 KVA unit substation will be installed by the electrical contractor inside the new electrical equipment room. Two existing transformers and primary switches and the existing 15KV pad mounted switch will need to be removed. The two existing 120/208V services will be back fed from the new unit substation. This project also includes a new ventilation system for the electrical equipment room. Included in the project is a labor agreement that will be executed between the lowest responsive/responsible bidder and the East Central Illinois Building & Construction Trade Council. A copy of the project labor agreement is included in the project bid documents, General Project Requirements.

Bid Dates
Bids for Divisions III, IV and V work will be received up to the hour of 10:00 a.m. prevailing time, on Tuesday August 3, 2004. Bids for Division I work will be received up to the hour of 2:00 p.m. prevailing time, on Tuesday August 3, 2004. The owner shall assign the contracts for Contract Divisions III, IV and V Work to the Contract Division I (General Contractor) in accordance with Article 6.2 of the General Conditions. (Refer to Articles 6.2 and 15 of the General Conditions for requirements concerning assignments of contracts.) Submit all proposals to the owner at:

The Board of Trustees of the University of Illinois
c/o Facilities & Services
1501 S. Oak Street
Champaign, IL 61820
Attn: Ed Scopel (ejscopel@oandm.uiuc.edu)

Bids will be received up to the hour of 2:00 PM local time, on Tuesday, August 3, 2004. Immediately after closing time for receiving bids, they will be opened publicly and read.

Pre-Bid Conference
A pre-bid conference will be held in Seminar Room 112H of Huff Hall, 1206 S. Fourth Street, Champaign, IL 61820 at 10:00 a.m. prevailing time on Thursday, July 22, 2004. Representatives of the owner and the Professional Services Consultant will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.

(Submitted by Kathe Shinham, State Purchasing Officer.)