Invitation for Construction Bid: F/A & Sprinkler Upgrade-Applied Health Science
Change Order
Published Thursday October 24, 2013
Contractor: Joseph Construction
Change Order Amount: $77,760.72

This change order is for services required on 7th floor due to A/E omissions in the project documents.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Thursday November 1, 2012
Awarded to:
Contractor: Joseph Construction, Lynwood, IL
Amount: $1,138,552
Division of Work: 1 - General (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Broadway Electric, Elk Grove Village, IL
Amount: $685,000
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: 6)
Terms:  One-time transaction
Contractor: Colfax, Chicago, IL
Amount: $63,600
Division of Work: 45 - Environmental (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 10
Comments:
Division 1-Successful responsive bidder:
22% MAFBE

Division 1-Unsuccessful responsive bidders:
J.L. Burke $1,679,829 (27.36% MAFBE)
Friedler $1,748,000 (22% MAFBE)

Division 5-Successful responsive bidder:
22% MAFBE

Division 5-Unsuccessful responsive bidders:
Jin Electric $689,000 (22% MAFBE)
Airport Electric $748,460 (22% MAFBE)
Argo Electric $785,000 (22.21% MAFBE)
McWilliams Electric $814,525 (22% MAFBE)
Webster Electric $865,000 (0% MAFBE)
DND Electric $994,624 (100% MAFBE)

Division 45-Successful responsive bidder:
20.44% MAFBE

Division 45-Unsuccessful responsive bidders:
Midway Contracting Group, LLC $96,000 (100% MAFBE)
NES $97,500 (100% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Tuesday, September 4, 2012
Project Description
Upgrade existing fire alarm system and fire sprinkler system to be compliant with latest codes. Complete interior demolition and upgrade to the 7th floor including asbestos abatement, new ceilings, lights, flooring, walls, interior finishes, window A/C units, new electrical service and distribution, plus new telecom infrastructure and distribution for the entire 7th floor.

Please see the attached file for more information.
Division 1 General Work
Sealed bids will be accepted at the address below until 10:30 AM, Thursday, September 27, 2012:
The Board of Trustees of the University of Illinois c/o
Office for Capital Programs - UIC
1140 South Paulina, M/C 892
Attention: Bradley W. Appier, brada@uillinois.edu; 312-996-1051
Chicago, IL 60612
Divisions 5 and 45
Sealed bids will be accepted at the address below until 10:30 AM, Tuesday, September 25, 2012:
The Board of Trustees of the University of Illinois c/o
Office for Capital Programs - UIC
1140 South Paulina, M/C 892
Attention: Bradley W. Appier, brada@uillinois.edu; 312-996-1051
Chicago, IL 60612
State Purchasing Officer - John Knittle

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.