Invitation for Construction Bid: NIH Lab/Research Facility Renovation - Dentistry
Change Order
Published Thursday May 23, 2013
Contractor: Airport Electric Company
Change Order Amount: $80,130.75

This change order is for task lighting at lab benches in new labs on 4th and 5th floors. This was originally part of the project scope which was removed due to budget constraints. As labs were constructed the existing lighting levels (50-60 foot-candle) were found to be at a level not acceptable for research work which is to be performed in the labs. New lighting level will be approximately 100 foot-candle.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Tuesday January 15, 2013
Contractor: Airport Electric Company
Change Order Amount: $60,433.87

This change order is for services to install temporary circuits/wiring for electrical shut downs needed to install equipment.
The State Purchasing Officer for this procurement is now John Knittle.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Thursday December 29, 2011
Awarded to:
Contractor: Joseph Construction Company, Lynwood, IL
Amount: $2,156,269
Division of Work: 1 - General (unsuccessful, responsive bidders: 7)
Terms:  One-time transaction
Contractor: Premier Mechanical, Inc., Addison, IL
Amount: $1,428,000
Division of Work: 3 - Heating Work (unsuccessful, responsive bidders: 6)
Terms:  One-time transaction
Contractor: Mechanical Concepts of Illinois, Inc., Romeoville, IL
Amount: $940,000
Division of Work: 4 - Ventilation Work (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: Airport Electric Company, Chicago, IL
Amount: $820,240
Division of Work: 5 - Electrical Work (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Universal Asbestos Removal, Inc., Lemont, IL
Amount: $179,000
Division of Work: 45-Enviro/Asbestos (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 21
Comments:
Division 1-Successful responsive bidder:
22.01% MAFBE

Division 1-Unsuccessful responsive bidders:
Barton Malow Company $2,945,600 (21.83% MAFBE)
Clune Construction Company $2,966,818 (27% MAFBE)
Old Veteran Construction, Inc. $3,094,900(22% MAFBE)
Chicago Commercial Contractors, LLC $3,491,734 (23.03% MAFBE)
Powers & Sons Construction Co. $3,252,700 (48.15% MAFBE)
The Lombard Company $3,126,000 (27.67% MAFBE)
IHC Construction Companies, LLC $2,947,959 (30.86% MAFBE)

Division 3-Successful responsive bidder:
22.41% MAFBE

Division 3-Unsuccessful responsive bidders:
Voris Mechanical, Inc.$1,626,000 (21.75% MAFBE)
Amber Mechanical Contractors, Inc. $1,715,500 (22.01% MAFBE)
Quality Control Systems, Inc. $1,776,840 (22.01% MAFBE)
Ideal Heating Co. $1,717,000 (22.13% MAFBE)
Monaco Mechanical, Inc. $1,657,000 (22.33% MAFBE)
F. E. Moran, Inc. $1,597,000 (10% MAFBE)

Division 4-Successful responsive bidder:
22.00% MAFBE

Division 4-Unsuccessful responsive bidders:
R. J. Olmen Company $1,140,298 (22.00% MAFBE)
Amber Mechanical Contractors, Inc. $1,353,000 (22% MAFBE)
Westside Mechanical, Inc. $1,193,000 (22.05% MAFBE)
Stern Corporation $1,190,000 (21.85% MAFBE)

Division 5-Successful responsive bidder:
22.00% MAFBE

Division 5-Unsuccessful responsive bidders:
Argo Electric, Inc. $1,143,000 (23.81% MAFBE)
McWilliams Electric Company, Inc. $1,125,773 (22% MAFBE)

Division 45-Successful responsive bidder:
100.00% MAFBE

Division 45-Unsuccessful responsive bidders:
Colfax Corporation $207,800 (0% MAFBE)
Midway Contracting Group, LLC $285,000 (0% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Thursday, October 27, 2011
Project Description
Reconfiguration of spaces on the first, fourth and fifth floors in the College of Dentistry (940) building to provide research operatories and support spaces, laboratories and support offices, conference rooms and equipment rooms, tissue culture rooms and an animal research facility; including, but not limited to, the design of new demising and partition walls, flooring, lighting and ceiling tile, secured entry (card reader) doors, doors, transoms and vision panels, lab benches and counters, scattered sink stations, fume hoods, X-ray equipment; HVAC, sprinkler, plumbing, electrical and data/telecom reconfiguration; and asbestos abatement.

See the attached file for more information.
Division 1 - General Work
Sealed bids will be accepted at the address below until 10:00 AM, Friday, November 18, 2011:
The Board of Trustees of the University of Illinois
Office for Capital Programs - UIC
1140 South Paulina
Attention: Robert E. Larson (robertl@uillinois.edu) 312-996-2556
Chicago, IL 60612
Divisions 2, 3, 4, 5, and 45
Sealed bids will be accepted at the address below until 10:00 AM, Thursday, November 17, 2011:
The Board of Trustees of the University of Illinois
Office for Capital Programs - UIC
1140 South Paulina
Attention: Robert E. Larson (robertl@uillinois.edu) 312-996-2556
Chicago, IL 60612

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.

Bulletin Navigation

 
To obtain documents, log on:
Specification Documents
  • BA940C10024Ad.pdf (88 KB)