University of Illinois at Chicago
Bid #BA942C12062
Invitation for Construction Bid: LHS 1st Flr Renovation & Modernize F/A & Sprinkler
Change Order
Published Friday September 25, 2015
Contractor: Joseph Construction Company
Change Order Amount: $80,559.29

This change order is for installation of fire alarm pull stations and ceiling/wall-mounted devices added per code.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info Published Tuesday February 17, 2015
Awarded to:
Contractor: Joseph Construction Company, Lynwood, IL
Amount: $1,535,271
Division of Work: 1-General Work (unsuccessful, responsive bidders: 6)
Terms:  One-time transaction
Contractor: F. E. Moran, Inc., Northbrook, IL
Amount: $167,800
Division of Work: 3-Heating Work (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: R. J. Olmen Company, Glenview, IL
Amount: $177,977
Division of Work: 4-Ventilation Work (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Airport Electric Company, Chicago, IL
Amount: $1,102,851
Division of Work: 5-Electrical Work (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 16
Comments:
Division 1-Successful, responsive bidder:
22% MAFBE

Division 1-Unsuccessful, responsive bidders:
The Bowa Group $1,655,754 (94.28% MAFBE)
PATH Construction Company $1,771,500 (20.32% MAFBE)
Chicago Commercial Construction $1,937,820.60 (22.31% MAFBE)
Friedler Construction Company $2,066,064 (23.50% MAFBE)
Paul Borg COnstruction, Inc. $2,109,136 (25.50% MAFBE)
K.R. Miller $2,495,680 (22.92% MAFBE)

Division 3-Successful, responsive bidder:
22% MAFBE

Division 3-Unsuccessful, responsive bidders:
Ideal Heating Company $193,333 (22.24% MAFBE)
Amber Mechanical Contractors $195,000 (21.69% MAFBE)
Voris Mechanical $208,900 (22% MAFBE)
Premier Mechanical $217,000 (22.12% MAFBE)

Division 4-Successful, responsive bidder:
22.19% MAFBE

Division 4-Unsuccessful, responsive bidders:
Stern Corporation $188,731 (22.14% MAFBE)
Amber Mechanical Contractors $257,600 (22.01% MAFBE)

Division 5-Successful, responsive bidder:
24% MAFBE

Division 5-Unsuccessful, responsive bidders:
Moran Electrical $1,202,440 (100% MAFBE)
Broadway Electric $1,240,300 (22% MAFBE)
Sharlen Electric $1,345,100 (23.34% MAFBE)
Public Electric Corporation $1,404,830 (22.17% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
This notice has been modified
Published Wednesday December 31, 2014
The bid opening date for Division 1 has been changed to January 22, 2015.

The bid opening date for Divisions 3-5 has been changed to January 21, 2015.
First published Tuesday, December 2, 2014
Project Description
1st floor: Remodel approx. 23,000 SF of existing library stack/study space, office spaces, conference rooms, and office services on the first floor of the Library of the Health Sciences (942 building) located at 1750 W. Polk St, Chicago. New spaces to include a reconfigured study space, quiet study space, conference rooms, classrooms, several meeting spaces, staff offices, relocated reference/service desk, vending/coffee area and technical services staff areas. F/A and sprinkler: Modernize the existing fire alarm system and install a new fire sprinkler system in the Library of the Health Sciences (942 building). An existing pre-action sprinkler system in the basement is to remain. The existing elevator recall system is to remain.

Please see the attached file for more information.
Division 1 - General Work
Sealed bids will be accepted at the address below until 10:00 AM, Thursday, January 22, 2015:
The Board of Trustees of the University of Illinois c/o
Office for Capital Programs - UIC
1140 South Paulina, M/C 892 Room 204
Attention: Michael Molnar / Eric Luchetta,ericl@uic.edu, (312) 355-5429
Chicago, IL 60612
Divisions 3, 4, and 5
Sealed bids will be accepted at the address below until 10:00 AM, Wednesday, January 21, 2015:
The Board of Trustees of the University of Illinois c/o
Office for Capital Programs - UIC
1140 South Paulina, M/C 892 Room 204
Attention: Michael Molnar / Eric Luchetta,ericl@uic.edu, (312) 355-5429
Chicago, IL 60612
State Purchasing Officer - John Knittle
All responses must include:
  • There is a BEP goal for this procurement. See solicitation documentation for details.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.