Bid #BA949C14045
Invitation for Construction Bid: UIH Hospital Mechanical and Electrical Upgrades
Change Order
Published Thursday April 12, 2018
Contractor: Ideal Heating
Change Order Amount: $262,191.09

This change order is for materials associated to add AHU S-6 and ER-6 back into the project. These were deleted via previous change order (#48).
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Thursday April 5, 2018
Contractor: Mechanical Inc.
Change Order Amount: $866,196.53

This change order is for materials associated to add AHU S-6 and ER-6 back into the project. These were deleted via previous change order (#48).
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Monday March 26, 2018
Contractor: Mechanical Inc.
Change Order Amount: $117,760.19

This change order is for labor costs associated with work to add AHU S-6 and ER-6 back into the project. These were deleted via previous change order (#48).
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info Published Tuesday March 29, 2016
Awarded to:
Contractor: CCC Commercial Construction, Chicago, IL
Amount: $995,000
Division of Work: 1 - General (unsuccessful, responsive bidders: 0)
Terms:  One-time transaction
Contractor: Ideal Heating, Brookfield, IL
Amount: $3,080,444
Division of Work: 3 - Htg AC Temp Cntr (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: Mechanical Inc., Freeport, IL
Amount: $6,204,000
Division of Work: 4 - Ventilation (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: Airport Electric, Chicago, IL
Amount: $230,662
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: 1)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 8
Comments:
Division 1 - Successful, responsive bidder:
27% MAFBE

Division 3 - Successful, responsive bidder:
23% MAFBE

Division 3 - Unsuccessful, responsive bidders:
Quality Control $3,396,000 (22% MAFBE)
FE Moran $3,612,000 (22% MAFBE)
Mechanical Inc. $4,459,000 (22% MAFBE)
Anchor Mechanical $4,763,136 (22% MAFBE)

Division 4 - Successful, responsive bidder:
22% MAFBE

Division 4 - Unsuccessful, responsive bidders:
Amber Mechanical $6,358,000 (19% MAFBE)
Quality Control $6,577,000 (22% MAFBE)
AMS $7,269,712 (12% MAFBE)

Division 5 - Successful, responsive bidder:
22% MAFBE

Division 5 - Unsuccessful, responsive bidder:
Moran Electric $338,785 (100% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
This notice has been modified
Published Tuesday January 12, 2016
The bid opening date for Division 1 has been changed to February 1, 2016.

The bid opening date for Divisions 3, 4, and 5 has been changed to January 27, 2016. The bid opening ROOM for Divisions 3, 4, and 5 has been changed to ROOM 245 of the Paulina Street Building.
First published Friday, December 4, 2015
Project Description
The project consists of phased replacements of up to eight (8) air handling units plus exhaust fans, electrical distribution, lighting, fire alarm, sprinkler, heat recovery system components, piping, and temperature control work associated with the air handling unit replacements. The air handling units will be replaced in a one-by-one fashion with downtime minimized for new unit tie-ins. New changeover chilled water piping will be connected to existing air handling units (AHU-1 and AHU-2). A new walkway suitable for wheeled carts will be installed on the roof to existing chillers, existing air handling units S-11 and S-7, and new air handling unit S-5. New maintenance access platform will be installed at the existing roof mounted chillers. Building wide pneumatic temperature controls will be replaced with digital electronic temperature control system. This includes controls and valves for existing terminal devices such as terminal boxes, booster coils, and induction units. Controls and valves for existing hydronic converters will be replaced. Controls and actuators for existing exhaust fans will be replaced. Isolation room pressure controls and utility meter monitoring will also be replaced.

This Project is located at: Corner of Taylor Street and Wood Street, Chicago, IL

Please see the attached file for more information.
Division 01 - General Work
Sealed bids will be accepted at the address below until 1:00 PM, Monday, February 1, 2016:
The Board of Trustees of the University of Illinois
c/o Office for Capital Programs
1140 South Paulina, Suite 204 MC 892
Attention: Gregory P. Quinn / Brad Appier - Project Manager, bappier@uic.edu, (312) 996-1051
Chicago, IL 60612
Divisions 3, 4 and 5
Sealed bids will be accepted at the address below until 10:30 AM, Wednesday, January 27, 2016:
The Board of Trustees of the University of Illinois
c/o Office for Capital Programs
1140 South Paulina, Suite 204 MC 892
Attention: Gregory P. Quinn / Brad Appier - Project Manager, bappier@uic.edu, (312) 996-1051
Chicago, IL 60612
State Purchasing Officer - John Knittle
All responses must include:
  • There is a BEP goal for this procurement. See solicitation documentation for details.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.

Bulletin Navigation

 
To obtain documents, log on:
Specification Documents
  • BA949C14045ad.pdf (89 KB)