To obtain documents, log on:
:
Not registered? Register me now
 

Public Higher Education Bulletin

 
University of Illinois at Urbana-Champaign
Bid #BAU06075
Invitation for Construction Bid: Roger Adams Laboratory - Phase I
Change Order
Published Thursday February 5, 2009
Contractor: Grunloh Construction, Inc.
Change Order amount: $27,402.65

This change order is for the demolition and installation of existing steam and condensate piping and relocation of exiting unit heater due to a piping/ductwork conflict.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Thursday March 27, 2008
Awarded to:
Contractor: Grunloh Construction, Inc., Effingham, IL
Amount: $1,025,000
Division of Work: #1 - General (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: A & R Mechanical Contractors, Inc., Urbana, IL
Amount: $140,278
Division of Work: #2 - Plumbing (unsuccessful, responsive bidders: 1)
Terms:  One-time transaction
Contractor: Davis-Houk Mechanical, Inc., Urbana, IL
Amount: $672,700
Division of Work: #3-Htg, AC, TempCont (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: King-Lar Company, Decatur, IL
Amount: $1,015,000
Division of Work: #4-Ventilation (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Glesco Electric, Inc., Urbana, IL
Amount: $504,471
Division of Work: #5 - Electrical (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: McDaniel Fire Systems, Inc., Champaign, IL
Amount: $74,470
Division of Work: #6 - Sprinkler (unsuccessful, responsive bidders: 1)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 12
The University award process may be delayed up to thirty days as this award goes through a state approval process.
This notice has been modified
Published Thursday January 17, 2008
Division 6-Sprinkler Work has been added to replace Division 19-Fire Protection Work which was removed.
First published Tuesday, January 15, 2008
Project Description
The project consists of renovation of approximately 18,030 square feet on the third and fourth floors of the 1947 Roger Adams Laboratory building at the University of Illinois Urbana-Champaign. The renovation consists of replacing lab casework, fume hoods, lab gas, wire way, cold rooms, x-ray lab, offices and other supporting spaces. It also includes related infrastructure upgrades and replacement of designated windows.

This project includes a project labor agreement that will be executed between the lowest responsive/ responsible bidder and the East Central Building & Construction Trades Council. A copy of the project labor agreement is included in the project bid documents, General Project Requirements.
Division #1 - General Work
Sealed bids will be accepted at the address below until 10:00 AM, Thursday, February 7, 2008:
The Board of Trustees of the University of Illinois
c/o Facilities & Services, Physical Plant Service Building
1501 S. Oak Street
Attn: Steven O'Connor (steveoc@fs.uiuc.edu)
Champaign, IL 61820
Divisions # 2, 3, 4, 5, 6
Sealed bids will be accepted at the address below until 10:00 AM, Tuesday, February 5, 2008:
The Board of Trustees of the University of Illinois
c/o Facilities & Services, Physical Plant Service Building
1501 S. Oak Street
Attn: Steven O'Connor (steveoc@fs.uiuc.edu)
Champaign, IL 61820
The Owner shall assign the contracts for Contract Divisions #2- Plumbing, #3-Heating, #4-Ventilation Work, #5-Electrical, and #6- Sprinkler Work to the Contract Division #1-General Contractor in accordance with Article 6.2 of the General Conditions. (Refer to Articles 6.2 and 15 of the General Conditions for requirements concerning assignments of contracts.)

Bid Document Sources
Bid documents have been prepared by Loebl Schlossman Hackl, Inc., 233 N. Michigan, (312) 565-4562, the professional services consultant. The bid documents may be obtained from the Professional Services Consultant by depositing a check in the amount of $110 for each set, payable to them OR non-cash plan deposit programs which are guaranteed by contractor associations are acceptable.

Bid Document Review Sets
For a complete list, please see the attached file.

Prequalification
Each bidder shall prequalify with the owner in accordance with the General Instructions to Bidders (Document 00200).

All bidders shall be prequalified with the owner. New bidders that are not prequalified shall prequalify using the owner's web-based Contractor Annual Prequalification System (CAPS)- http://przm.apps.uillinois.edu/

The project will be administered using the owner's web-based project management system. PRZM was developed to maximize the potential of the Internet in allowing project team members to access and exchange project information. PRZM supports team collaboration in management and interaction, as well as team member empowerment on a multi-layer security system.
Minimum PRZM user requirements are as follows:
  • Personal Computer: Microprocessor speed of 100mhz or higher, 32Mb RAM, and a monitor capable of at least 800 x 600 pixel resolution.
  • Internet Browser: Microsoft Internet Explorer version 4.0 or higher is recommended.
  • E-mail: PRZM requires the user to have a valid e-mail account.
  • Software: At various stages of PRZM, users will be required to attach their documents to PRZM.
  • Computer-Aided Drawing (CAD) viewer
Pre-Bid Meeting
A pre-bid meeting will be held in Chemical and Life Science Laboratory at 9:00 a.m. Room A466 prevailing time on Wednesday, January 30, 2008 Representatives of the owner and the professional services consultant will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.

Bid Opening
Immediately after the closing time for receiving bids, all proposals will be publicly opened, read, and tabulated at Physical Plant Service Building, 1501 S. Oak, Room 128 on February 5th, and Conference Room 127 on February 7th. Noted errors, omissions and defects will be announced. Bids received after closing time will be returned unopened. The public opening and reading is for information only and is not construed as acceptance or rejection of any bid.

Bid Acceptance or Rejection
The owner reserves the right to reject any or all bids or any part thereof, to waive any informalities in the bidding, and to accept the bids deemed to be in the best interests of the owner after all bids have been examined and evaluated.

Statutory Requirements
The successful bidder will be required to comply with all laws, statutes, regulations, ordinances, rulings or enactments of any governmental authority that are applicable to the work or to the project. The successful bidder shall pay prevailing wages and shall utilize equal employment opportunity hiring practices in connection with this project.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

Bulletin Navigation

 
To obtain documents, log on:
Other Public Documents
  • BAU06075BidSets.pdf (9 KB)