Awarded to:Contractor: Poettker Construction Company, Breese, IL
Amount: $11,369,000
Division of Work: 1 - General (unsuccessful, responsive bidders: 1)
Terms: One-time transaction
Contractor: A&R Mechanical Contractors, Inc., Urbana, IL
Amount: $2,690,000
Division of Work: 2 - Plumbing (unsuccessful, responsive bidders: 2)
Terms: One-time transaction
Contractor: Davis-Houk Mechanical, Inc., Urbana, IL
Amount: $3,074,000
Division of Work: 3 - Htg AC TempCntrl (unsuccessful, responsive bidders: 2)
Terms: One-time transaction
Contractor: A&R Mechanical Contractors, Inc., Urbana, IL
Amount: $2,747,250
Division of Work: 4 - Ventilation (unsuccessful, responsive bidders: 1)
Terms: One-time transaction
Contractor: Jamerson & Bauwens Electrical Contractors, Inc., Northbrook, IL
Amount: $5,078,146
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: 2)
Terms: One-time transaction
Contractor: Automatic Fire Sprinkler, LLC, Rockford, IL
Amount: $344,573
Division of Work: 6 - Sprinkler (unsuccessful, responsive bidders: 2)
Terms: One-time transaction
Contractor: Williams Brothers Construction, Inc., Peoria, IL
Amount: $3,395,000
Division of Work: 17 - Drywall (unsuccessful, responsive bidders: 1)
Terms: One-time transaction
Contractor: Otto Baum Company, Inc., Morton, IL
Amount: $1,619,000
Division of Work: 23 - Masonry (unsuccessful, responsive bidders: 0)
Terms: One-time transaction
Number of unsuccessful, responsive bidders: 11
Comments:
Division 1 - Successful, responsive bidder:
21% MAFBE
Division 1 - Unsuccessful, responsive bidder:
Petry-Kuhne $13,102,400 (22% MAFBE)
Division 2 - Successful, responsive bidder:
20% MAFBE
Division 2 - Unsuccessful, responsive bidders:
G.A. Rich $2,690,000 (20% MAFBE)
Davis-Houk $2,982,040 (20% MAFBE)
Division 3 - Successful, responsive bidder:
20% MAFBE
Division 3 - Unsuccessful, responsive bidders:
A&R Mechanical $3,123,800 (20% MAFBE)
Reliable $3,129,080 (20% MAFBE)
Division 4 - Successful, responsive bidder:
20% MAFBE
Division 4 - Unsuccessful, responsive bidder:
Reliable $3,744,200 (20% MAFBE)
Division 5 - Successful, responsive bidder:
20% MAFBE
Division 5 - Unsuccessful, responsive bidders:
Bodine $5,817,710 (20% MAFBE)
Oberlander $5,818,000 (20% MAFBE)
Division 6 - Successful, responsive bidder:
20% MAFBE
Division 6 - Unsuccessful, responsive bidders:
Prairie Fire $534,867 (100% MAFBE)
Superior Fire $537,800 (20% MAFBE)
Division 17 - Successful, responsive bidder:
20% MAFBE
Division 17 - Unsuccessful, responsive bidder:
Poettker Construction $3,506,000 (22% MAFBE)
Division 23 - Successful, responsive bidder:
20% MAFBE
The University award process may be delayed up to thirty days as this award goes through a state approval process.