Bid #BAU12197-2
Invitation for Construction Bid: Ikenberry Residence Hall #3 Site Infrastructure
Change Order
Published Tuesday January 5, 2016
Contractor: Duce Construction Company
Change Order Amount: $95,000

This is the CHANGE ORDER with the final amount for the field directive posted on March 23, 2015. This CHANGE ORDER is for a concrete patio, curbing and associated utiity relocations between the two turf fields.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Monday March 23, 2015
Contractor: Duce Construction Company
Change Order Amount: $95,000

This is an amount for a FIELD DIRECTIVE for a concrete patio, curbing and associated utiity relocations between the two turf fields.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info Published Tuesday November 26, 2013
Awarded to:
Contractor: Nicholas & Associates, Inc., Mount Prospect, IL
Amount: $5,098,000
Division of Work: 27-Site Work (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 3
Comments:
Division 27-Successful responsive bidder:
16.05% MAFBE

Division 27-Unsuccessful responsive bidders:
Mid-States General & Mechanical $5,733,000 (6.50% MAFBE)
Stark Excavating $5,816,530 (15.40% MAFBE)
Duce Construction $6,590,000 (15% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info Published Thursday November 7, 2013
Awarded to:
Contractor: Duce Construction Company, Champaign, IL
Amount: $452,000
Division of Work: 34 - Site Work (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 3
Comments:
Division 34-Successful responsive bidder:
15% MAFBE

Division 34-Unsuccessful responsive bidders:
A&R Mechanical Services $473,024 (15.10% MAFBE)
Stark Excavating, Inc. $631,500 (15% MAFBE)
Mid-States General & Mechanical $743,000 (17.80% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
This notice has been modified
Published Friday September 20, 2013
A second mandatory pre-bid will be held on Wednesday, September 25, 2013, at 8 AM. If a contractor attended the first mandatory pre-bid meeting, they are not required to attend this pre-bid meeting to be eligible to bid the project. Location: Student Dining and Residential Programs Building, 2009 Hopkins Seminar Room, 301 E. Gregory Drive, Champaign, Illinois.
First published Thursday, September 5, 2013
Project Description
Residence Hall No. 3 is the next phase of a multi-phase project to replace the existing housing within Ikenberry Commons. The four-story building with partial basement is approximately 155,000 square feet. This first phase includes site utilities, stormwater detention system, and artificial turf fields. The project has a goal of LEED Gold Certification.

Please see the attached file for more information.
Divisions 27 and 34
Sealed bids will be accepted at the address below until 2:00 PM, Friday, October 4, 2013:
The Board of Trustees of the University of Illinois c/o
Facilities and Services - UIUC
1501 South Oak Street, Room 115
Attention: Elizabeth Stegmaier, elizabet@illinois.edu, (217) 265-6471
Champaign, IL 61820
State Purchasing Officer - John Knittle
All responses must include:
  • There is a BEP goal for this procurement. See solicitation documentation for details.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.

Bulletin Navigation

 
To obtain documents, log on:
Specification Documents
  • BAU12197-2ad.pdf (63 KB)