Awarded to:Contractor: Bishop Brothers, Peoria, IL
Amount: $776,500
Division of Work: 1-General Work (unsuccessful, responsive bidders: 9)
Terms: One-time transaction
Contractor: Reliable Plumbing and Heating, Champaign, IL
Amount: $109,800
Division of Work: 2-Plumbing Work (unsuccessful, responsive bidders: 5)
Terms: One-time transaction
Contractor: A&R Mechanical Contractors Inc., Urbana, IL
Amount: $168,900
Division of Work: 3-Heat AC Temp Work (unsuccessful, responsive bidders: 4)
Terms: One-time transaction
Contractor: A&R Mechanical Contractors Inc., Urbana, IL
Amount: $270,000
Division of Work: 4-Ventilation Work (unsuccessful, responsive bidders: 5)
Terms: One-time transaction
Contractor: Glesco Electric Inc., Urbana, IL
Amount: $168,939
Division of Work: 5-Electrical Work (unsuccessful, responsive bidders: 2)
Terms: One-time transaction
Number of unsuccessful, responsive bidders: 25
Comments:
Division 1-Successful, responsive bidder:
19.05% MAFBE
Division 1-Unsuccessful, responsive bidders:
CORE Construction $882,000 (17.59% MAFBE)
Path Construction $903,100 (15.50% MAFBE)
Grunloh Construction, Inc. $915,000 (17.25% MAFBE)
Vanguard Construction $921,900 (48.27% MAFBE)
Felmley-Dickerson $969,900 (0% MAFBE)
Commercial Builders, Inc. $992,000 (15.38% MAFBE)
Johnco Construction Inc. $1,031,700 (15.44% MAFBE)
Williams Brothers Construction, Inc. $1,084,000 (15.04% MAFBE)
Poettker Construction, Inc. $1,142,000 (15.19% MAFBE)
Division 2-Successful, responsive bidder:
15.06% MAFBE
Division 2-Unsuccessful, responsive bidders:
X-Treme Mechanical, Inc. $123,000 (15% MAFBE)
E.L. Pruitt Co. $139,268.37 (15.73% MAFBE)
A&R Mechanical Contractors, Inc. $145,000 (15% MAFBE)
G.A. Rich & Sons, Inc. $146,200 (15.73% MAFBE)
Davis-Houk Mechanical Inc. $154,997 (15% MAFBE)
Division 3-Successful, responsive bidder:
15.06% MAFBE
Division 3-Unsuccessful, responsive bidders:
E.L. Pruitt Company $186,648 (15.02% MAFBE)
X-Treme Mechanical, Inc. $193,965 (14% MAFBE)
Reliable Plumbing and Heating Co. $194,740 (15% MAFBE)
Davis-Houk Mechanical, Inc. $197,500 (15% MAFBE)
Division 4-Successful, responsive bidder:
15.02% MAFBE
Division 4-Unsuccessful, responsive bidders:
Reliable Plumbing & Heating Co. $270,880 (15% MAFBE)
King-Lar Co. $277,000 (15% MAFBE)
E.L. Pruitt Company $321,545 (15.40% MAFBE)
Commercial Refrigeration $322,575 (13.70% MAFBE)
Industrial Services of Illinois, Inc. $361,800 (10.49% MAFBE)
Division 5-Successful, responsive bidder:
15% MAFBE
Division 5-Unsuccessful, responsive bidders:
Central Illinois Electric Company $176,500 (15% MAFBE)
Commercial Electric $340,862 (15.06% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.