Awarded to:Contractor: Path Construction Company, INc., Arlington Heights, IL
Amount: $2,957,000
Division of Work: 1 - General (unsuccessful, responsive bidders: 3)
Terms: One-time transaction
Contractor: Davis-Houk Mechanical, Inc., Urbana, IL
Amount: $375,500
Division of Work: 3-Htg AC Temp Cntrl (unsuccessful, responsive bidders: 1)
Terms: One-time transaction
Contractor: Davis-Houk Mechanical, Inc., Urbana, IL
Amount: $373,960
Division of Work: 4 - Ventilation (unsuccessful, responsive bidders: 3)
Terms: One-time transaction
Contractor: Glesco Electric, Inc., Urbana, IL
Amount: $175,000
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: 0)
Terms: One-time transaction
Number of unsuccessful, responsive bidders: 7
Comments:
Division 1 - Successful, responsive bidder:
16.06% MAFBE
Division 1 - Unsuccessful, responsive bidders:
Grunloh Construction $3,018,000 (16.57% MAFBE)
Barton Malow $3,130,000 (46.98% MAFBE)
Femley-Dickerson Company $3,432,500 (0% MAFBE)
Division 3 - Successful, responsive bidder:
15% MAFBE
Division 3 - Unsuccessful, responsive bidder:
Reliable Plumbing $408,200 (15% MAFBE)
Division 4 - Successful, responsive bidder:
15% MAFBE
Division 4 - Unsuccessful, responsive bidders:
J.A. Fritch $388,700 (15% MAFBE)
Reliable Plumbing $405,680 (15% MAFBE)
A&R Mechanical $430,937 (15% MAFBE)
Division 5 - Successful, responsive bidder:
15% MAFBE