Addendum 2 forms a part of the contract and contract documents and modifies the original contract documents dated 10/29/20. Acknowledge receipt of this addendum in space provided on Bid Form.
Clarifications Item 1 The Owner will procure the infilled synthetic turf and its installation for both new buildings outside of the scope of this project. This scope is removed from the bidding documents. The bidding Contractor will still be responsible for subgrade, compaction, elevations, stone substrates, geotextile fabric, etc. below the turf. New drawing details and specifications are being included in this addendum to identify this change.
Amendments to the Drawings Item 2 Volume #1, Sheet IPF101, Detail A - Infilled Synthetic Turf Profile: REPLACE with detail attached to this addendum.
Item 3 Volume #2, Sheet IPF101, Detail A - Infilled Synthetic Turf Profile: REPLACE with detail attached to this addendum.
Amendments to the Specifications
Item 4 Section 32 1824 - Synthetic Turf Playing Field Surfacing: REPLACE section in its entirety with revised section attached to this addendum.