Invitation for Construction Bid: UIC Forum and James J. Stukel Towers
Change Order
Published Monday November 29, 2010
Contractor: Gurtz Electric Co., Arlington Heights, IL
Change Order amount: $571,120

This change order is to allow close out of the project.
The buyer for this procurement is now Mary White, (217) 244-8518.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Friday January 27, 2006
Awarded to:
Contractor: Waukegan Steel Sales, Waukegan, IL
Amount: $3,025,596
Division of Work: Division 24 - Metal Fabrications and Metal Stairs Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: LeJeune Steel
Amount: $6,361,000
Division of Work: Division 28 - Structural Steel Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Flood Testing, Chicago, IL
Amount: $205,793
Division of Work: Division 51A - Testing and Inspections Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 7
Comments:
The low bid amount was accepted for each division.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Tuesday December 20, 2005
Awarded to:
Contractor: Cerami Construction, Melrose Park, IL
Amount: $3,220,000
Division of Work: Division I - General Conditions for Trades Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Chas F. Bruckner & Sons, Inc., Chicago, IL
Amount: $5,089,990
Division of Work: Division II Plumbing Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: AMS Mechanical System, Burr Ridge, IL
Amount: $4,895,775
Division of Work: Division III - Hydronic Piping Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Admiral Heating & Ventilation, Inc., Hillside, IL
Amount: $3,928,000
Division of Work: Division IV - Ventilation Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Gurtz Electric Co., Arlington Heights, IL
Amount: $12,621,800
Division of Work: Division V - Electrical Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Automatic Building Controls, Inc., Park Ridge, IL
Amount: $793,000
Division of Work: Division VII - Temperature Controls Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Goebel Forming, Inc., Roselle, IL
Amount: $13,799,165
Division of Work: Division XV-B - Cast in Place Concrete Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Northstar Fire Protection Co., Broadview, IL
Amount: $1,860,000
Division of Work: Division XIX - Fire Supression Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Illinois Masonry Corp., Lake Zurick, IL
Amount: $6,052,000
Division of Work: Division XXIII - Masonry Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Boswell Building Contractors, Bensenville, IL
Amount: $669,300
Division of Work: Division XXIV-B Louvers Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: E.W. Olsen Roofing, Markham, IL
Amount: $1,429,480
Division of Work: Division XXVI - Modified Bitumen and Hot Fluid Applied Roof Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: All American Exterior Solutions, Inc., Lake Zurich, IL
Amount: $562,700
Division of Work: Division XXVI-A - Metal Roofing Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Harrington Excavation & Construction, Alsip, IL
Amount: $593,132
Division of Work: Division XXXII - Utility Site Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Contractor: Klein-Dickert Kenosha, Inc, Kenosha, WI
Amount: $7,575,297
Division of Work: Division XXXV - Curtain Wall Work (unsuccessful, responsive bidders: )
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 33
Comments:
The low bid amount was accepted for each division.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Wednesday, June 22, 2005
Project Description

The Board of Trustees of U of Illinois Facilities Planning and Programs hereby requests sealed bids for construction work on the South Campus Mixed Use Development project at the Chicago campus project (Bid # PRQ698-704-04-A).

  • Bid Package - Earthwork, Primary Specification Sections - 02230 Site Clearing, 02300 Earthwork, 02925 Soil, and Soil Procurement, Estimated Construction Value - $740,000
  • Bid Package - Caissons, Bid Package Primary Specification Sections - 02466 Drilled Piers (Caissons), Estimated Construction Value - $1,800,000
  • Bid Package - Site Utility Services, Primary Specification Sections - 02510 Water Distribution, 02530 Sanitary Sewerage, 02620 Subdrainage, 02630 Storm Drainage, Estimated Construction Value - $560,000
  • Bid Package - Cast-in-Place Concrete, Primary Specification Sections - 03100 Concrete Formwork, 03200 Concrete Reinforcement, 03300 Cast-in-place Concrete, Estimated Construction Value - $11,200,000
  • Bid Package - Metal Fabrications and Metal Stairs, Primary Specification Sections - 05500 Metal Fabrications, 05511 Metal Stairs, Estimated Construction Value - $1,250,000
  • Bid Package - Sheet Waterproofing, Primary Specification Sections -07131 Self-Adhering Sheet Waterproofing, Estimated Construction Value - $4,000
  • Bid Package - Elevators , Primary Specification Sections - 14210 Electric Traction Elevators, 14240 Hydraulic Elevators, Estimated Construction Value - $2,260,000
  • Bid Package - Cast-in-Place Concrete Foundations, Primary Specification Sections - 03100 Concrete Formwork, 03200 Concrete Reinforcement, 03300 Cast-in-place Concrete, Estimated Construction Value - $690,000
  • Bid Package - Demolition, Primary Specification Sections - 02071 Selective Demolition, Estimated Construction Value - $40,000
  • Bid Package - Testing and Inspection Services, Primary Specification Sections - 01410 Testing and Inspection Services, Estimated Construction Value - $475,000
University of Illinois at Chicago hereby requests expression of interest and prequalification of bidders for the South Campus Mixed Use Development project at the Chicago campus.

This project, totaling approximately 432,000 square feet, consists of a residence hall with housing for approximately 754 students in four towers of four, seven, eleven and thirteen levels, a convocation center (UIC Forum) with an assembly facility seating approximately 3,000 in arena-style or 1,000 in banquet-style, a dining facility complete with kitchen, an event center, study rooms, and retail spaces. The project site is located on a full city block at the southeast corner of Roosevelt Road and Halsted Street. The total construction cost is estimated to be approximately $95 million. Construction is scheduled to commence in August of 2005.
Sealed bids will be accepted at the address below until 2:00 PM, Wednesday, August 3, 2005:
Office for Capital Programs
1140 South Paulina Street
Chicago, IL 60612-7217

Bid Document Sources
Bid documents have been prepared by Hellmuth, Obata & Kassabaum, Inc., 30 West Monroe Street, Chicago IL 60603, phone: (312) 782-1000 and Vasilko, Hauserman & Associates, 330 North Wabash Avenue, Suite 2123, Chicago IL 60611, phone (312) 755-9800.

Bid Document Review Sets
Bid documents will be made available to pre-qualified bidders through Power Construction Company, LLC, 2360 Palmer Drive, Schaumburg, IL 60173 phone (847) 925-1300, hereinafter called the Construction Manager.

Prequalification
All bidders shall be prequalified with the owner. New bidders that are not prequalified shall prequalify using the owner's web-based Contractor Annual Prequalification System (CAPS)- http://notes.ocp.uiuc.edu:8888/


Copies of the prequalification applications may be obtained from the Construction Manager by sending a fax expressing interest to (847) 925-1372 or an email expressing interest to nadams@pcec.net. Faxes and emails should be sent to the attention of Nate Adams, Assistant Project Manager. Prequalification for the project's bid packages described above will begin June 21, 2005. Prequalification applications for the project's bid packages described above are due no later than 4:00 PM, prevailing time, on July 11, 2005. Prequalification is only required of prime contractors for each bid package. All applicants will also be required to provide adequate payment and performance bonding in accordance with the University's requirements. Criteria for evaluation of applicants will include company organization, relevant work experience, volume and type of work, financial standing, planning and scheduling capabilities, safety record, affirmative action and labor compliance records, and other trade specific qualifications.

Notice of Prequalification
After the prequalification deadline, all applicants who are prequalified for the project will be notified by the Construction Manager.

Bid Opening
Immediately after the closing time for receiving bids, they will be opened, publicly read, and tabulated in the Office for Capital Programs Conference Room 244, 1140 South Paulina Street, Chicago, Illinois 60612-7217.

Bid Acceptance or Rejection
The Owner reserves the right to reject any or all bids or any part thereof, to waive any informalities in the bidding, and to accept the bids deemed to be in the best interests of the Owner after all bids have been examined and evaluated.

Statutory Requirements
The successful bidder will be required to comply with all laws, statutes, regulations, ordinances, rulings or enactments of any governmental authority that are applicable to the work or to the project. The successful bidder shall pay prevailing wages and shall utilize equal employment opportunity hiring practices in connection with this project.

Contracting and Employment Opportunities
The University of Illinois at Chicago has established the following goals and requirement for the contracting and employment opportunities generated by this project:

  • A goal that 45% of the contracts be given to minority-owned, women-owned or local business enterprises.
  • A goal that 50% of the employment opportunities be given to minorities, women and local residents.
  • A requirement that 50% of the employment opportunities be given to City of Chicago residents. (In case of non-compliance, 1/20 of 1 percent (0.0005) of your contract sum shall be surrendered in payment for each percentage less than the 50% City residency requirement.)

Immediately after closing time for receiving bids, they will be opened publicly and read.

For bidding documents and further information, contact

The University of Illinois at Chicago
312 413-8722

Pre-Bid Meeting
Information and details concerning the pre-bid meeting will be included in the bid documents distributed by the Construction Manager to the pre-qualified bidders.

(Submitted by Kathe Shinham, State Purchasing Officer.)

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.