Request for Professional Services Qualifications (QBS): Mechanical & Electrical Upgrades-Pharmacy College
Amendment
Published Tuesday October 2, 2012
Consultant: Affiliated Engineers, Inc.
Amendment Amount: $226,200

The scope of work for this amendment is to renovate the laboratories on the 3rd, 4th and 5th floors which will include new ceilings, lights, floors, casework and fume hoods.
This amendment corrects and replaces the amendment posted below on September 19, 2012.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Amendment
Published Wednesday September 19, 2012
Consultant: Affiliated Engineers, Inc.
Amendment Amount: $226,200

The scope of work will be used to abate substantial asbestos in the ceilings to allow for the removal and replacement of the existing ceilings and lights, and for new floors and casework to be installed on the third through fifth floors.


The State Purchasing Officer for this procurement is now John Knittle.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Monday September 12, 2011
Awarded to:
Consultant: Affiliated Engineers, Inc., Chicago, IL
Amount: $790,000
Terms:
An estimated start date of 9/12/2011 through 8/17/2013
Renewals:
None
Number of Unsuccessful, Responsive Respondents: 2
This award corrects and replaces the award posted below on August 18, 2011.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Thursday August 18, 2011
Awarded to:
Consultant: Affiliated Engineers, Inc., Chicago, IL
Amount: $790,000
Terms:  One-time transaction
Number of Unsuccessful, Responsive Respondents: 2
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Thursday, March 24, 2011
Project Description
Provide new primary building electrical service and upgraded primary distribution to each floor. Replace and up-size the existing chilled water pump. Replace the existing 5 air handling units serving the East Wing of the building.

In addition, the laboratories located on the 3rd, 4th and 5th floors of the east wing will be upgraded on an in-kind basis.

Please see the attached file for more information.
Letter Submission
Qualifications and supporting materials will be accepted at the address below until 4:00 PM, Monday April 11, 2011:

Office for Capital Programs
1140 South Paulina Street
Attention: Bradley W. Appiér (brada@uillinois.edu, 312.996-1051)
Chicago, IL 60612

Selection will be consistent with the Architectural, Engineering, and Land Surveying Qualifications Based Selection Act (30 ILCS 535/1).

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.

Bulletin Navigation

 
To obtain documents, log on:
Specification Documents
  • PSS924C11013Ad.pdf (36 KB)