Bid #R075731

Invitation for Construction Bid: Steam and Condensate Line Replacement

Change Order
Published Thursday September 27, 2007
 
Change order amount: $25,682

The change order is due to undiscovered buried utilities and omissions from the original as-built plans which necessitates extensive changes in the scope of work including, but not limited to, excavations, removal of abandoned steam and condensate lines and the installation of additional condensate line.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info
Published Monday May 7, 2007
 
Awarded to:
Contractor:  Frank Millard and Company, Inc., Burlington, IA
Amount:  $89,100
Terms:   One-time transaction
Number of Unsuccessful, Responsive Bidders: 1
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Monday April 16, 2007
Sealed bids will be accepted at the address below until 2:00 PM, Tuesday May 1, 2007:
227 Sherman Hall
1 University Circle
Macomb, IL 61455
A pr-bid meeting will be held April 23, 2007 at 10:00 am local time in Sherman Hall 277. A site visit will be conducted immediately following the prebid meeting.
This project is subject to the Illinois Prevailing Wage Act.
For additional information, contact:
Theresa Roegge
227 Sherman Hall
1 University Circle
Western Illinois University
Macomb, IL 61455
Phone: (309) 298-1819
FAX: (309) 298-1927
E-Mail: TD-Roegge@wiu.edu

Bulletin Navigation

 
To obtain documents, log on:
Other Public Documents
  • R075731.pdf (861 KB)