Awarded to:Contractor: Laverdiere Construction Inc, Macomb, IL
Amount: An estimated $592,400
Division of Work: General (unsuccessful, responsive bidders: 4)
Terms:
An estimated start date of 10/9/2017 through 8/31/2018
Renewals:
None
Contractor: Dries Brothers Plumbing Inc, Peoria, IL
Amount: An estimated $69,800
Division of Work: Plumbing (unsuccessful, responsive bidders: 0)
Terms:
An estimated start date of 10/9/2017 through 8/31/2018
Renewals:
None
Contractor: Arnold Brothers Heating and Cooling, Macomb, IL
Amount: An estimated $43,600
Division of Work: Mechanical (unsuccessful, responsive bidders: 1)
Terms:
An estimated start date of 10/9/2017 through 8/31/2018
Renewals:
None
Contractor: Frank Millard & Company Inc, Burlington, IA
Amount: An estimated $22,000
Division of Work: Ventilation (unsuccessful, responsive bidders: 1)
Terms:
An estimated start date of 10/9/2017 through 8/31/2018
Renewals:
None
Contractor: TEGCO Inc (dba Schaefer Electric Inc), Peoria, IL
Amount: An estimated $90,310
Division of Work: Electrical (unsuccessful, responsive bidders: 4)
Terms:
An estimated start date of 10/9/2017 through 8/31/2018
Renewals:
None
Number of unsuccessful, responsive bidders: 10
The University award process may be delayed up to thirty days as this award goes through a state approval process.