Chicago State University
Bid #0909dh
Invitation for Construction Bid: Temperature Control
Award InfoPublished Friday December 19, 2008
Awarded to:
Contractor: PRECISION CONTROL SYSTEM ,INC., GRIFFITH, IN
Amount: $111,600
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 4
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Wednesday, December 3, 2008
Project Description
Austin AECOM, on behalf of the Chicago State University, requests that Temperature Control contractors submit their qualifications for the following trade package for Phase 2 of the Chicago State University College of Pharmacy, Conversion and Renovation of Douglas Hall Project, a 15,000 sq. ft. portion of the conversion of the 3rd floor of Douglas Hall into a College of Pharmacy facility.
Tempature Control
Sealed bids will be accepted at the address below until 11:00 AM, Friday, December 19, 2008:
Cook Administration Building, Room 111
9501 South King Drive
Chicago, IL 60628-1598

For additional information, contact:
Nate Tindall
Chicago State University
Cook Administration Building, Rm. 111
9501 South King Drive
Chicago State University
Chicago, IL 60628-1598
Phone: (733) 995-2424
E-Mail: NE-Tindall@csu.edu
All responses must include:
  • Submit two copies of the response as defined in the specifications.
  • Sealed envelopes containing the bids have the bid number and project title on the envelope.