Request for Information: Prequalification for Thomas M. Siebel Center

Change Order
Published Friday March 5, 2004
 
Change order amount: $42,477

This change to Petry-Kuhne Company, is for general conditions work on the dumpsters, cleaning, and general carpentry.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday March 5, 2004
 
Change order amount: $71,853

This change to Central IL Erectors, a Division of Petry-Kuhne, is for miscellaneous work on the monumental stair rails; there was a change in the material and size of handrails on S5.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday March 5, 2004
 
Change order amount: $95,071

This change to Central IL Erectors, a Division of Petry-Kuhne, is for miscellaneous metal work on the change in stair S5 stringer size and shape.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Friday March 5, 2004
 
Change order amount: $59,532

This change to Petry-Kuhne Company is for providing general conditions work per EWA 71.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Thursday January 8, 2004
 
Change order amount: $32,147

This change to Carter Construction Services, Inc. is for drywall work on the frame above butt glazing.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info
Published Wednesday March 20, 2002
 
Awarded to:
Vendor:  Multiple contractors
Amount:  $47,305,383
Terms:   One-time transaction
Number of Unsuccessful, Responsive Bidders: 77
Comments:
For additional details, go to the Capital Programs website at: http://www.uocp.uillinois.edu.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Tuesday June 5, 2001
Sealed responses will be accepted at the address below until 4:00 PM, Friday July 6, 2001:
University of Illinois at Urbana-Champaign
207 Henry Administration Building
506 South Wright Street
Urbana, IL 61801-3684

Project Description
The project consists of the construction of a new Computer Sciences classroom building. The building is approximately 250,000 square feet and is a steel frame with masonry/face brick and curtain wall skin.

Prequalification
The bid documents will be provided to prequalified bidders by LZT Associates, Inc., 124 S. W. Adams St., Suite 450, Peoria, IL 61602, (309-673-3100), hereinafter called the architect/engineer.

The prequalification process begins with the prospective bidders' submittal of a Prequalification Application. Copies of the application may be obtained from Turner Construction Company, 701 Devonshire Drive, C-49, Suite 103G, Champaign, IL 61820, 217-353-7890, Attention: Steve Street, hereinafter called the Construction Manager. The prequalification deadline is 4:00 p.m., prevailing time on Friday, June 29, 2001. Prequalification applications received after the deadline will be returned unopened to the applicant.

After the prequalification deadline, all those applicants who are prequalified for the project will be notified by the construction manager. Bid documents will be distributed by the architect/engineer to only those applicants who are prequalified.

(Submitted by Katharine Kral, State Purchasing Officer.)

Bulletin Navigation

 
No documents are available.