Change order
amount: $95,614.62
The change is for miscellaneous items for the close-out.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change order
amount: $202,978
The cost is for design changes to provide energy savings for an exterior cold water loop piping for the facility.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Awarded to:
Contractor: Multiple contractors:
- Siciliano, Springfield ($5,047,914) for Division I - General Work
- Petersburg Plumbing and Heating, Petersburg ($424,626) for Division II - Plumbing Work
- Pipco, Peoria, IL ($104,700), for Division III - Fire Protection Work
- Petersburg Plumbing and Heating, Petersburg ($823,656) for Division IV - Heating Piping, Refrigeration & Temperature Work
- Henson Robininson, Springfield ($133,724) for Division V - Ventilation Work
- Egizii, Springfield ($994,000) for Division VI - Electrical Work
Amount:
Total of $7,528,620
Terms: One-time transaction
Number of Unsuccessful, Responsive Bidders:
22
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published
Wednesday April 19, 2000
Sealed bids will be accepted at the address below until
2:00 PM,
Monday May 22, 2000:
University of Illinois at Urbana-Champaign
207 Henry Administration Building
506 South Wright Street
Urbana,
IL
61801-3684
The Board of Trustees of
U of Illinois Facilities Planning and Programs
hereby requests sealed bids for construction work on the
Capital Scholars - Freshman/Sophomore Housing - Springfield.
Project Description
The project consists of a new three-story, 226-bed, 60,000 square foot residence hall, constructed of a brick veneer over concrete block, with pre-cast concrete floor decking.
Bid Proposals
Bids will be received up to the hour of 2:00 p.m. prevailing time, on Thursday, May 18, 2000, for Division II through Division VI work.
Bids will be received up to the hour of 2:00 p.m. prevailing time, on Monday, May 22, 2000, for Division I work. Submit all proposals to the Board of Trustees at:
University of Illinois Department of Physical Planning and Operations
Building A, Room 1
P.O. Box 19243
Springfield, IL 62794-9243
Attention: David Barrows, Director
email: barrows.dave@uis.edu
Bids will be received up to the hour of
2:00 PM
local time, on
Monday, May 22, 2000.
Immediately after closing time for receiving bids, they will be opened publicly and read.
A pre-bid conference will be held on the campus of the University of Illinois at Springfield, Conference Room F, on the first level of the Public Affairs Center, at 10:30 a.m. prevailing time on Tuesday, May 2, 2000. Representatives of the owner and the architect/engineer will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.