Invitation for Construction Bid: NCSA Petascale Computing Facility Phase 2
Change Order
Published Friday January 29, 2010
Contractor: Rathje Enterprises, Inc. dba Bodine Electric of Champaign
Change Order amount: $165,540.40

This change order is to purchase UPS system for project as per user request.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Wednesday December 9, 2009
Contractor: Siemens Building Technologies, Inc.
Change Order amount: $95,200

This change order is to provide meters, transmitters and control valves for chilled water.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Wednesday November 4, 2009
Contractor: Rathje Enterprises, Inc. dba Bodine Electric of Champaign
Change Order amount: $117,603.26

Installation of 2 tiered network & power basket type cable tray system.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Tuesday August 11, 2009
Contractor: Rathje Enterprises, Inc. dba Bodine Electric of Champaign
Change Order amount: $63,497.96

This change order is to furnish & install TVSS devices (over-voltage protection) on 19 unit substations.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Monday July 20, 2009
Contractor: A & R Mechanical Contractors Inc.
Change Order amount: $69,749.42

This change order is to correct and enhance the performance of the heating/AC system for Mechanical Rooms 1030 and 1030B. There is currently insufficient heating capacity in the AHU coils for the larger amount of OA make-up air required.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Change Order
Published Wednesday May 6, 2009
Contractor: A & R Mechanical Contractors Inc.
Change Order amount: $78,110.93

This change order is for the heat exchange revisions required by the Architect.
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award InfoPublished Tuesday November 18, 2008
Awarded to:
Contractor: Core Construction Services of Illinois, Morton, IL
Amount: $5,646,000
Division of Work: 1 - General (unsuccessful, responsive bidders: 6)
Terms:  One-time transaction
Contractor: Davis-Houk Mechanical Inc., Urbana, IL
Amount: $707,070
Division of Work: 2 - Plumbing (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: A & R Mechanical Contractors Inc., Urbana, IL
Amount: $5,771,000
Division of Work: 3 - Heating A/C (unsuccessful, responsive bidders: 1)
Terms:  One-time transaction
Contractor: A & R Mechanical Contractors Inc., Urbana, IL
Amount: $1,418,950
Division of Work: 4 - Ventilation (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: Rathje Enterprises, Inc. dba Bodine Electric of Champaign, Champaign, IL
Amount: $7,138,800
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: 5)
Terms:  One-time transaction
Contractor: Automatic Fire Sprinkler, LLC, Normal, IL
Amount: $313,700
Division of Work: 6 - Sprinkler (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: Siemens Building Technologies, Inc., Bloomington, IL
Amount: $1,281,100
Division of Work: 7-TemperatureControl (unsuccessful, responsive bidders: 1)
Terms:  One-time transaction
Contractor: Carter Construction Services, Inc., Champaign, IL
Amount: $847,300
Division of Work: 17 - Drywall (unsuccessful, responsive bidders: 1)
Terms:  One-time transaction
Contractor: J.J. Braker & Sons, Inc., Morton, IL
Amount: $990,748
Division of Work: 23 - Masonry (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: Stark Excavating, Inc., Champaign, IL
Amount: $274,100
Division of Work: 34-Utilities Site (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 29
The University award process may be delayed up to thirty days as this award goes through a state approval process.
This notice has been modified
Published Friday October 10, 2008
The bid opening date has been changed to October 16, 2008, at 1:00 PM CST.
This notice has been modified
Published Thursday October 2, 2008
The bid opening date has been changed to October 14, 2008.

Division 44 has been removed.
First published Friday, September 12, 2008
Project Description
The project consists of an approximately 90,000 square foot state-of-the-art building designed to provide a secure and efficient operating environment for the Petascale system, supporting cyber-infrastructure and associated support and research personnel. The Petascale facility will become home for the worlds fastest supercomputer at 10 PetaFLOPs (or a thousand trillion floating point operations per second). This machine will have the computing power of the current top 500 supercomputers in the world. The building has been designed according to University of Illinois at Urbana-Champaign Building Standards and Design Guidelines and will be a hardened building and site designed to withstand an F3 (165 mph) level tornado. The site location was chosen due to its close proximity to the existing Abbott Power Plant and the Oak Street Chiller Plant. This adjacency allows for economical utility distribution, as well as reliable and redundant power and cooling sources for the facility. The Petascale facility is being designed to a LEED Silver level.

Phase 2 shall consist of General Work; Plumbing Work; Heating and A/C; Ventilation Work; Electrical Work; Sprinkler Work; Temperature Control Work; Drywall Work; Masonry Work and Utilities Site Work.

This project includes a Project Labor Agreement that will be executed between the lowest responsible/responsive bidder and the East Central Illinois Building and Construction Trades Council. A copy of the Project Labor Agreement is included in the Project Bid Documents, General Project Requirements. The Project will be managed using the owners' web-based Construction Management System PRZM.
Divisions 1-7, 17, 23, 34
Sealed bids will be accepted at the address below until 1:00 PM, Thursday, October 16, 2008:
The Board of Trustees of the University of Illinois
c/o Facilities and Services
1501 S. Oak Street
Attn: Richard Drew (rgdrew@illinois.edu)
Champaign, IL 61820
Divisions to be bid include #1 General Work, #2 Plumbing Work, #3 Heating A/C Work, #4 Ventilation Work, #5 Electrical Work, #6 Sprinkler Work, #7 Temperature Control Work, #17 Drywall Work, #23 Masonry Work, and #34 Utilities Site Work.

Bid Document Sources
Bid documents have been prepared by Clayco, Inc., One Trans Am Plaza Drive, Suite 400, Oakbrook Terrace, IL 60181, Chad Derus, (630) 620 9494, the Construction Manager. The bid documents may be obtained from Dean's Blueprint, 404 East University Avenue, Champaign, IL 61820 (217) 359 3261 by depositing a check in the amount of $500 for each set, payable to the construction manager OR non-cash plan deposit programs which are guaranteed by contractor associations are acceptable.

BP#4 Division 1: General Work - 2 Sets
BP#5 Division 2: Plumbing Work - 2 Sets
BP#6 Division 3: Heating A/C Work - 2 Sets
BP#7 Division 4: Ventilation Work - 2 Sets
BP#8 Division 5: Electrical Work - 2 Sets
BP#9 Division 6: Sprinkler Work - 2 Sets
BP#10 Division 7: Temperature Controls Work - 2 Sets
BP#11 Division 17: Drywall/Ceilings/Painting Work - 2 Sets
BP#12 Division 23: Masonry Work - 1 Set
BP#13 Division 34: Utilities Site Work - 1 Set

Bid Document Review Sets
For a complete list, please see the attached file.

Prequalification
Each bidder shall prequalify with the owner in accordance with the General Instructions to Bidders (Document 00200).

All bidders shall be prequalified with the owner. New bidders that are not prequalified shall prequalify using the owner's web-based Contractor Annual Prequalification System (CAPS)- http://przm.apps.uillinois.edu/

The project will be administered using the owner's web-based project management system. PRZM was developed to maximize the potential of the Internet in allowing project team members to access and exchange project information. PRZM supports team collaboration in management and interaction, as well as team member empowerment on a multi-layer security system.
Minimum PRZM user requirements are as follows:
  • Personal Computer: Microprocessor speed of 100mhz or higher, 32Mb RAM, and a monitor capable of at least 800 x 600 pixel resolution.
  • Internet Browser: Microsoft Internet Explorer version 4.0 or higher is recommended.
  • E-mail: PRZM requires the user to have a valid e-mail account.
  • Software: At various stages of PRZM, users will be required to attach their documents to PRZM.
  • Computer-Aided Drawing (CAD) viewer
Pre-Bid Meeting
A pre-bid meeting will be held in NCSA Building, Conference Room 1030, 1205 West Clark, Urbana, IL 61801 at 1:00 p.m. prevailing time on Tuesday, September 30, 2008. Representatives of the owner and the professional services consultant will be present to answer questions regarding the project and bidding procedures. All prospective bidders are urged to attend.

Bid Opening
Immediately after the closing time for receiving bids, all proposals will be publicly opened, read, and tabulated at Physical Plant Service Building, 1501 South Oak Street, Champaign, IL 61820, Conference Room 128. Noted errors, omissions and defects will be announced. Bids received after closing time will be returned unopened. The public opening and reading is for information only and is not construed as acceptance or rejection of any bid.

Bid Acceptance or Rejection
The owner reserves the right to reject any or all bids or any part thereof, to waive any informalities in the bidding, and to accept the bids deemed to be in the best interests of the owner after all bids have been examined and evaluated.

Statutory Requirements
The successful bidder will be required to comply with all laws, statutes, regulations, ordinances, rulings or enactments of any governmental authority that are applicable to the work or to the project. The successful bidder shall pay prevailing wages and shall utilize equal employment opportunity hiring practices in connection with this project.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.