Awarded to:Contractor: Williams Brothers Construction, Inc., Peoria, IL
Amount: $1,987,600
Division of Work: General (unsuccessful, responsive bidders: 6)
Terms: One-time transaction
Contractor: Commercial Mechanical, Inc., Dunlap, IL
Amount: $454,000
Division of Work: Heating (unsuccessful, responsive bidders: 3)
Terms: One-time transaction
Contractor: Fleming Electric, Inc., East Peoria, IL
Amount: $302,000
Division of Work: Electrical (unsuccessful, responsive bidders: 3)
Terms: One-time transaction
Contractor: Mechanical Service of Galesburg, Inc., Galesburg, IL
Amount: $191,900
Division of Work: Ventilation (unsuccessful, responsive bidders: 4)
Terms: One-time transaction
Contractor: Warner Plumbing, Inc., E. Peoria, IL
Amount: $808,200
Division of Work: Plumbing (unsuccessful, responsive bidders: 3)
Terms: One-time transaction
Contractor: Continental Fire Springkler Co., Davenporta, IA
Amount: $24,880
Division of Work: Fire Protection (unsuccessful, responsive bidders: 4)
Terms: One-time transaction
Number of unsuccessful, responsive bidders: 22
Comments:
Two bids were rejected for not providing a valid Board of Elections certificate.
The University award process may be delayed up to thirty days as this award goes through a state approval process.