Awarded to:
Contractor: Central Illinois Electric Company, Pesotum, IL
Amount: $115,900
Division of Work: 5-Electrical Work (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 3
Comments:
Division 5-Successful, responsive bidder:
13.73% MAFBE

Division 5-Unsuccessful, responsive bidders:
Potter Electric $118,836 (15% MAFBE)
Anderson Electric $144,300 (15% MAFBE)
Glesco Electric $180,380 (15.02% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
Award Info Published Friday September 19, 2014
Awarded to:
Contractor: English Brothers Company, Champaign, IL
Amount: $417,000
Division of Work: 1-General Work (unsuccessful, responsive bidders: 6)
Terms:  One-time transaction
Contractor: Reliable Plumbing and Heating Co., Champaign, IL
Amount: $122,980
Division of Work: 2-Plumbing Work (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Contractor: Davis-Houk Mechanical, Inc., Urbana, IL
Amount: $104,000
Division of Work: 3-Heat AC Temp Work (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: B.E.C. Mechanical, Inc., Ogden, IL
Amount: $131,522
Division of Work: 4-Ventilation Work (unsuccessful, responsive bidders: 4)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 17
Comments:
Division 1-Successful, responsive bidder:
26.98% MAFBE

Division 1-Unsuccessful, responsive bidders:
Grunloh Construction $423,000 (26.60% MAFBE)
Bishop Bros., Inc. $423,232 (30.05% MAFBE)
Felmley-Dickerson $424,000 (26.53% MAFBE)
Path Construction $458,000 (24.02% MAFBE)
Commercial Builders $474,900 (23.69% MAFBE)
CORE Construction $489,000 (23.01% MAFBE)

Division 2-Successful, responsive bidder:
15% MAFBE

Division 2-Unsuccessful, responsive bidders:
Davis-Houk $123,321 (15% MAFBE)
A&R Mechanical $141,940 (15.01% MAFBE)
X-TREME Mechanical $147,850 (15.02% MAFBE)
G.A. Rich & Sons $170,444 (15.25% MAFBE)

Division 3-Successful, responsive bidder:
21.63% MAFBE

Division 3-Unsuccessful, responsive bidders:
A&R Mechanical $106,000 (15.09% MAFBE)
E.L. Pruitt $106,700 (21.09% MAFBE)
Reliable Plumbing $113,730 (15% MAFBE)

Division 4-Successful, responsive bidder:
15.78% MAFBE

Division 4-Unsuccessful, responsive bidders:
Reliable Plumbing and Heating Co. $134,910 (15% MAFBE)
King Lar $144,900 (15% MAFBE)
A&R Mechanical $151,200 (15% MAFBE)
E.L. Pruitt $168,800 (15.05% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
This notice has been modified
Published Thursday July 24, 2014
The bid opening date, time and location for Division 1 have been changed to August 19, 2014 at 2:00 p.m. in Conference Room 1830.

The bid opening date and time for Divisions 2-5 have been changed to August 15, 2014 at 2:00 p.m.
First published Friday, July 11, 2014
Project Description
Project work includes the renovation of approximately 2600 SF of undeveloped interior space on the fourth floor of Newmark Laboratory. The project will provide research laboratories and accessory laboratory spaces for two assistant UI professors, as well as a departmental utility room to service these research spaces, allowing the connection of these new research spaces with a new air handling system being installed by another UI project on the fourth floor of Newmark Lab. This laboratory renovation will include a bio-safety level 2 laboratory space to support research. Project will include the design and construction of two labs, including lab utilities: compressed air, natural gas, H+C water sources with new local HW heaters, sanitary drain connections, extension of fire sprinkler system into lab and mechanical support spaces, and an emergency shower station. The ventilation system for both labs shall accommodate the inclusion of new laboratory fume hoods (one with vented acid storage cabinet below) and one laminar flow hood.

Please see the attached file for more information.
Division 1 - General Work
Sealed bids will be accepted at the address below until 2:00 PM, Tuesday, August 19, 2014:
The Board of Trustees of the University of Illinois c/o
Facilities and Services - UIUC
1501 South Oak Street
Attention: Matt Firmand, firmand@illinois.edu, (217)244-6821
Champaign, IL 61820
Divisions 2, 3, 4, and 5
Sealed bids will be accepted at the address below until 2:00 PM, Friday, August 15, 2014:
The Board of Trustees of the University of Illinois c/o
Facilities and Services - UIUC
1501 South Oak Street
Attention: Matt Firmand, firmand@illinois.edu, (217)244-6821
Champaign, IL 61820
State Purchasing Officer - John Knittle
All responses must include:
  • There is a BEP goal for this procurement. See solicitation documentation for details.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.

Documents

To obtain any of the following documents, please log into your Bulletin account.

Specification Documents

  • BAU14006ad.pdf (187 KB)

Conflict of Interest Document

  • COI_CentralIllinoisElectricBAU14006092314.pdf (308 KB)
  • COI_Davis-HoukBAU14006090914.pdf (293 KB)
Log In