Invitation for Construction Bid: Bevier Hall - Infrastructure Renovation Phase 2
Award Info Published Thursday January 11, 2018
Awarded to:
Contractor: Petry-Kuhne Company, Champaign, IL
Amount: $638,700
Division of Work: 1 - General (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: A&R Mechanical Contractors, Inc., Urbana, IL
Amount: $522,071
Division of Work: 3 - Htg AC Temp Cntr (unsuccessful, responsive bidders: 2)
Terms:  One-time transaction
Contractor: Davis-Houk Mechanical, Inc., Urbana, IL
Amount: $566,000
Division of Work: 4 - Ventilation (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Contractor: Potter Electric Service Inc., Urbana, IL
Amount: $908,950
Division of Work: 5 - Electrical (unsuccessful, responsive bidders: 3)
Terms:  One-time transaction
Number of unsuccessful, responsive bidders: 10
Comments:
Division 1 - Successful, responsive bidder:
21% MAFBE

Division 1 - Unsuccessful, responsive bidders:
Commercial Builders $711,400 (20% MAFBE)
Grunloh Construction $815,000 (20% MAFBE)

Division 3 - Successful, responsive bidder:
20% MAFBE

Division 3 - Unsuccessful, responsive bidders:
Davis-Houk $534,990 (20% MAFBE)
Reliable $552,440 (20% MAFBE)

Division 4 - Successful, responsive bidder:
20% MAFBE

Division 4 - Unsuccessful, responsive bidders:
Reliable $566,300 (20% MAFBE)
J.A. Fritch $583,250 (20% MAFBE)
A&R Mechanical $589,723 (21% MAFBE)

Division 5 - Successful, responsive bidder:
20% MAFBE

Division 5 - Unsuccessful, responsive bidders:
Commercial Electric $941,315 (20% MAFBE)
Bodine Electric $941,481 (20% MAFBE)
Oberlander Electric $1,099,953 (20% MAFBE)
The University award process may be delayed up to thirty days as this award goes through a state approval process.
First published Tuesday, October 10, 2017
Project Description
The project consists of the second phase of infrastructure renovation at Bevier Hall. Items covered within this project include: 1. Replacement of existing main electrical service unit substations in the existing basement electrical room. 2. Replacement of air handling units S-1 and S-2 in a newly constructed basement mechanical room. 3. Replacement of exhaust fans, variable frequency drives, and controllers that support S-1 and S-2. 4. Installation of Variable Air Volume boxes to service occupied areas supplied from S-1 and S-2. 5. Replacement of temperature control systems in affected areas.

A MANDATORY pre-bid meeting will be held in Bevier Hall, room 286, 905 South Goodwin Avenue, Urbana, Illinois 61801 on 10/18/17 at 9:30 A.M. prevailing time. All prospective bidders are REQUIRED to attend.

This Project is located at: Bevier Hall Building 0158, 905 South Goodwin Avenue, Urbana, Illinois 61801.

See the attached file for more information.
Division 1 - General Work
Sealed bids will be accepted at the address below until 2:30 PM, Thursday, November 16, 2017:
The Board of Trustees of the University of Illinois
c/o Facilities and Services
1501 South Oak Street, Room 115
Attention: Angela King, aking06@illinois.edu, (217)300-3997
Champaign, IL 61820
Divisions 3, 4, 5
Sealed bids will be accepted at the address below until 2:30 PM, Tuesday, November 14, 2017:
The Board of Trustees of the University of Illinois
c/o Facilities and Services
1501 South Oak Street, Room 115
Attention: Angela King, aking06@illinois.edu, (217)300-3997
Champaign, IL 61820
State Purchasing Officer - John Knittle
All responses must include:
  • There is a BEP goal for this procurement. See solicitation documentation for details.
  • The contract(s) for this solicitation could exceed $50,000 annually.

This transaction is subject to the State Board of Elections registration and certification requirements of Public Act 095-0971.

The State of Illinois has a policy to encourage prospective vendors to hire qualified veterans, minorities, females, persons with disabilities and ex-offenders.

Documents

To obtain any of the following documents, please log into your Bulletin account.

Specification Documents

  • BAU16062ad.pdf (81 KB)

Conflict of Interest Document

  • COIARMechanicalBAU160621217.pdf (181 KB)
  • COIDavisHoukBAU160621217.pdf (841 KB)
Log In