Invitation for Construction Bid: Cardinal Court furnace replacement
#LB022504: Cardinal Court furnace replacementIllinois State University
Bid #LB022504
Invitation for Construction Bid: Cardinal Court furnace replacement
Award Info Published Wednesday March 17, 2004
National Construction Services
Amount: $53,432
Terms: One-time transaction
Unsuccessful respondent...
ISU
Construction
Awarded
Opening Date: 2/25/04
Invitation for Construction Bid: Computer Access-Watterson Towers-electrical
#LB02260200: Computer Access-Watterson Towers-electricalIllinois State University
Bid #LB02260200
Invitation for Construction Bid: Computer Access-Watterson Towers-electrical
Award Info Published Thursday April 18, 2002
Institutional Network Communications
Amount: $1,264,780
Terms: One-time transa...
ISU
Construction
Awarded
Opening Date: 2/26/02
Invitation for Construction Bid: asbestos abatement for Wright Hall
#LB02270200: asbestos abatement for Wright HallIllinois State University
Bid #LB02270200
Invitation for Construction Bid: asbestos abatement for Wright Hall
Award Info Published Monday April 22, 2002
the two contractors given below
Amount: $13,400 (Champion Environmental-Base Bid A1) and $70,107 (T...
ISU
Construction
Awarded
Opening Date: 2/27/02
Invitation for Construction Bid: Watterson Towers Electrical Renovation - Phase 4
#LB03130200: Watterson Towers Electrical Renovation - Phase 4Illinois State University
Bid #LB03130200
Invitation for Construction Bid: Watterson Towers Electrical Renovation - Phase 4
Award Info Published Monday May 13, 2002
Foster Jacob Inc.
Amount: $327,720
Terms: One-time transaction
Unsucces...
ISU
Construction
Awarded
Opening Date: 3/20/02
Invitation for Construction Bid: Asbestos Abatement
#LB031804: Asbestos AbatementIllinois State University
Bid #LB031804
Invitation for Construction Bid: Asbestos Abatement
Award Info Published Monday June 28, 2004
Mavo Systems
Amount: $45,580
Terms: One-time transaction
Unsuccessful respondents (6) The University award process may be delayed up t...
ISU
Construction
Awarded
Opening Date: 3/18/04
Invitation for Construction Bid: Haynie Hall Pipe Insulation
#LB03200101: Haynie Hall Pipe InsulationIllinois State University
Bid #LB03200101
Invitation for Construction Bid: Haynie Hall Pipe Insulation
Award Info Published Tuesday March 20, 2001
M & O Insulation
Amount: $28,055
Terms: One-time transaction
Unsuccessful respondents () The University award ...
ISU
Construction
Awarded
Opening Date: 3/20/01
Invitation for Construction Bid: rebid for CVA elevator upgrade
#LB032604: rebid for CVA elevator upgradeIllinois State University
Bid #LB032604
Invitation for Construction Bid: rebid for CVA elevator upgrade
Award Info Published Friday May 14, 2004
KONE, Inc.
Amount: $49,872
Terms: One-time transaction
Unsuccessful respondents () The University award process...
ISU
Construction
Awarded
Opening Date: 3/26/04
Invitation for Construction Bid: Entry Work
#LB0327: Entry WorkIllinois State University
Bid #LB0327
Invitation for Construction Bid: Entry Work
Award Info Published Tuesday April 29, 2003
Bishop Brothers Inc.
Amount: $99,855
Terms: One-time transaction
Unsuccessful respondents () The University award process may be delayed up to thirty da...
ISU
Construction
Awarded
Opening Date: 3/27/03
Invitation for Construction Bid: University Farm at Lexington Sheep Facility
#LB0328: University Farm at Lexington Sheep FacilityIllinois State University
Bid #LB0328
Invitation for Construction Bid: University Farm at Lexington Sheep Facility
Award Info Published Saturday June 14, 2003
J & J Equipment
Amount: $46,225
Terms: One-time transaction
Unsuccessful respondents (...
ISU
Construction
Awarded
Opening Date: 3/28/03
Announcement of a Sole Source Purchase
#LB03300100: upgrades to the power plant substationsIllinois State University
SoleSource #LB03300100
Announcement of a Sole Source Purchase
Award Info Published Friday March 30, 2001
Illinois Power Company
Amount: $395,349
Terms: One-time transaction The University award process may be delayed up...
ISU
SoleSource
Awarded